Permit Application Status
PRFS202107592
You will only be able to view fees or view conditions if you are a contact on the permit application.
Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.
There are no deposits or bonds for this permit application.
| Inspection |
Outcome |
Requested |
Scheduled |
Date Complete |
|
Fire Rough-in Inspection
|
Partial Pass
|
12/8/2021 (10:00 - 12:00)
|
12/8/2021 (PM)
|
12/10/2021
|
|
Hydro Test Start
|
Partial Pass
|
5/18/2022 (8:00 - 10:00)
|
5/18/2022 (AM)
|
05/23/2022
|
|
Hydro Test End
|
Partial Pass
|
5/18/2022 (8:00 - 10:00)
|
5/18/2022 (AM)
|
05/23/2022
|
|
Hydro Test Start
|
Passed
|
|
|
12/01/2023
|
|
Fire Inspection Final
|
Passed
|
|
|
12/01/2023
|
|
Acceptance Test Inspection
|
Passed
|
|
|
12/01/2023
|
|
Fire Rough-in Inspection
|
Passed
|
|
|
12/01/2023
|
|
Hydro Test End
|
Passed
|
|
|
12/01/2023
|