PRFS202107981
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
09/13/2021
Must verify hangers in hard lid areas are In the proper orientation and the the structure is strong enough for that application. There is still open pipe and I must verify connections were made. Ceilings were in place in some areas so I was unable to see if brackets were secured to grid.
|
||||
Fire Inspection Final | Pending | |||
Fire Rough-in Inspection | Partial Pass | 8/18/2021 (8:00 - 10:00) | 8/18/2021 (AM) | 08/18/2021 |
Corrections:
Miscellaneous/Other
Carried Forward
08/18/2021
Must verify hangers in hard lid areas are In the proper orientation and the the structure is strong enough for that application. There is still open pipe and I must verify connections were made. Ceilings were in place in some areas so I was unable to see if brackets were secured to grid.
|
||||
Hydro Test Start | Passed | 8/30/2021 (10:00 - 12:00) | 8/30/2021 (AM) | 09/03/2021 |
Hydro Test End | Passed | 8/30/2021 (12:30 - 2:30) | 8/30/2021 (PM) | 09/03/2021 |
Fire Inspection Final | Not Ready | 9/10/2021 (8:00 - 10:00) | 9/10/2021 (AM) | 09/13/2021 |
Fire Rough-in Inspection | Not Ready | 9/10/2021 (8:00 - 10:00) | 9/10/2021 (AM) | 09/13/2021 |
Corrections:
Miscellaneous/Other
Carried Forward
09/13/2021
Must verify hangers in hard lid areas are In the proper orientation and the the structure is strong enough for that application. There is still open pipe and I must verify connections were made. Ceilings were in place in some areas so I was unable to see if brackets were secured to grid.
|