PRFS202111170
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Hydro Test Start | Passed | 10/14/2021 (10:00 - 12:00) | 10/14/2021 (AM) | 10/14/2021 |
Hydro Test End | Passed | 10/14/2021 (12:30 - 2:30) | 10/14/2021 (PM) | 10/14/2021 |
Fire Rough-in Inspection | Partial Pass | 10/14/2021 | ||
Needs to add 4 heads in the 1st row of wet system due to obstructions. | ||||
Fire Inspection Final | Not Ready | 10/26/2021 (12:30 - 2:30) | 10/26/2021 (PM) | 11/19/2021 |
24-hr Air Test Start | Passed | 12/08/2021 | ||
24-hr Air Test End | Passed | 12/08/2021 | ||
Fire Rough-in Inspection | Passed | 12/08/2021 | ||
Fire Inspection Final | Passed | 12/08/2021 |