Permit Application Status

PRFS202202127


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRFS202202127
Fire Suppression System
Expired
ROERS MINNESOTA OPPORTUNITY ZONE FUND LLC
Other
Design and install a new NFPA 13 fire sprinkler system in a new 6 story apartment building.
03/03/2022
04/19/2022
12/06/2023

Locations

Permits

Permit Number: PRFS202202127

Fire Suppression System
Expired
04/19/2022
12/06/2023

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Acceptance Test Inspection Pending
Fire Inspection Final Pending
Fire Rough-in Inspection Pending
Fire Rough-in Inspection Partial Pass 9/21/2022 (2:30 - 3:30) 9/21/2022 (PM) 09/22/2022
phase 1 6th floor OK
Fire Rough-in Inspection Partial Pass 9/29/2022 (8:00 - 10:00) 9/29/2022 (AM) 09/30/2022
Fire Rough-in Inspection Partial Pass 10/6/2022 (8:00 - 10:00) 10/6/2022 (AM) 10/06/2022
4th floor phase 1 ok
Fire Rough-in Inspection Partial Pass 10/13/2022 (12:30 - 2:30) 10/13/2022 (PM) 10/19/2022
Fire Rough-in Inspection Partial Pass 10/27/2022 (8:00 - 10:00) 10/27/2022 (AM) 10/27/2022
Fire Rough-in Inspection Partial Pass 11/17/2022 (10:00 - 12:00) 11/17/2022 (AM) 11/22/2022
Fire Rough-in Inspection Partial Pass 11/30/2022 (2:30 - 3:30) 11/30/2022 (PM) 12/01/2022
Fire Rough-in Inspection Partial Pass 12/8/2022 (12:30 - 2:30) 12/8/2022 (PM) 12/13/2022
Fire Rough-in Inspection Partial Pass 12/15/2022 (12:30 - 2:30) 12/15/2022 (PM) 12/19/2022
Fire Rough-in Inspection Partial Pass 12/28/2022 (8:00 - 10:00) 12/28/2022 (AM) 12/30/2022
Fire Rough-in Inspection Partial Pass 2/1/2023 (8:00 - 10:00) 2/1/2023 (AM) 02/02/2023
Fire Rough-in Inspection Partial Pass 2/28/2023 (2:30 - 3:30) 2/28/2023 (PM) 03/06/2023
Fire Rough-in Inspection Not Ready 4/4/2023 (12:30 - 2:30) 4/4/2023 (PM) 04/04/2023
Fire Rough-in Inspection Partial Pass 4/6/2023 (10:00 - 12:00) 4/6/2023 (AM) 04/06/2023
Hydro Test Start Passed 5/31/2023 (8:00 - 10:00) 5/31/2023 (AM) 06/09/2023
Hydro Test End Passed 5/31/2023 (10:00 - 12:00) 5/31/2023 (PM) 06/09/2023