PRFS202202954
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Fire Rough-in Inspection | Partial Pass | 5/25/2022 (10:00 - 12:00) | 5/25/2022 (AM) | 05/25/2022 |
| Ok to cover 2 back rooms and coffee counter area. | ||||
| Hydro Test Start | Passed | 7/1/2022 (10:00 - 12:00) | 7/1/2022 (AM) | 07/01/2022 |
| Hydro Test End | Passed | 7/1/2022 (12:30 - 2:30) | 7/1/2022 (PM) | 07/01/2022 |
| Fire Rough-in Inspection | Passed w/ Conditions | 7/1/2022 (12:30 - 2:30) | 7/1/2022 (PM) | 07/01/2022 |
| Multiple painted sprinkler heads in visitor center. Shall be replaced. | ||||
| Fire Inspection Final | Passed | 08/30/2023 | ||