PRFS202204016
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Fire Rough-in Inspection | Partial Pass | 06/03/2022 | ||
| OK to cover "sound stage 2, maker studio 1, maker studio 2." | ||||
| Fire Rough-in Inspection | Partial Pass | 06/08/2022 | ||
| OK to cover large room across from dock door 51. | ||||
| Fire Rough-in Inspection | Partial Pass | 8/1/2022 (8:00 - 10:00) | 8/1/2022 (AM) | 08/01/2022 |
| Fire Rough-in Inspection | Partial Pass | 10/24/2022 (AM) | 10/25/2022 | |
| Coverage needed 2nd floor under duct in center area. Flex head bracket not properly secured in room near exterior door 8. | ||||
| Fire Rough-in Inspection | Passed | 08/15/2023 | ||
| Acceptance Test Inspection | Passed | 08/15/2023 | ||
| Fire Inspection Final | Passed | 08/15/2023 | ||