PRFS202310331
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Partial Pass | 12/21/2023 (10:00 - 12:00) | 12/21/2023 (AM) | 12/21/2023 |
Ok to cover the second floor soffit areas except the women's locker room. Need to adjust and add coverage. Also discussed the utility room (trash & recycling) sprinkler coverage for the room and under the doors. Contractor is working on a solution. | ||||
Fire Rough-in Inspection | Partial Pass | 12/27/2023 (12:30 - 2:30) | 12/27/2023 (PM) | 12/27/2023 |
Ok to cover 2nd floor women's locker room and 2nd floor elevator lobby soffit. | ||||
Fire Rough-in Inspection | Partial Pass | 1/10/2024 (8:00 - 10:00) | 1/10/2024 (AM) | 01/12/2024 |
Service bay, Tire storage ESFR, 3rd floor restrooms - approved. | ||||
Fire Rough-in Inspection | Partial Pass | 1/18/2024 (8:00 - 10:00) | 1/18/2024 (AM) | 01/18/2024 |
Showroom 2nd floor/high ceiling area. Flex hose install verified and approved. Ok to began hard-lid install. | ||||
Fire Rough-in Inspection | Partial Pass | 3/20/2024 (2:30 - 3:30) | 3/20/2024 (PM) | 03/20/2024 |
2nd and 3rd floor complete except for east rooms neat the skyway on both levels. | ||||
Hydro Test Start | Passed | 03/26/2024 | ||
Starting psi 220 (needed for 200 psi at 3rd floor) | ||||
Hydro Test End | Passed | 03/26/2024 | ||
Ending psi 220. | ||||
Fire Rough-in Inspection | Partial Pass | 4/1/2024 (10:00 - 12:00) | 4/1/2024 (AM) | 04/02/2024 |
2nd floor complete. Only remaining area is 1st floor showroom center area with wood trim ceiling. | ||||
Fire Rough-in Inspection | Partial Pass | 04/09/2024 | ||
1st floor east overhead door area. | ||||
Acceptance Test Inspection | Passed | 04/12/2024 | ||
Fire Rough-in Inspection | Passed | 04/15/2024 | ||
Fire Inspection Final | Passed | 04/15/2024 |