PRFS202311298
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Partial Pass | 1/29/2024 (10:00 - 12:00) | 1/29/2024 (AM) | 01/31/2024 |
Fire Rough-in Inspection | Partial Pass | 2/26/2024 (2:30 - 3:30) | 2/26/2024 (PM) | 02/28/2024 |
Fire Rough-in Inspection | Partial Pass | 3/6/2024 (Afternoon) | 3/6/2024 (PM) | 03/14/2024 |
Fire Rough-in Inspection | Partial Pass | 5/23/2024 (8:00 - 10:00) | 5/23/2024 (AM) | 05/24/2024 |
Hydro Test Start | Passed | 8/27/2024 | 8/27/2024 (PM) | 09/03/2024 |
Hydro Test End | Passed | 8/27/2024 | 8/27/2024 (PM) | 09/03/2024 |
Fire Inspection Final | Partial Pass | 9/16/2024 (Afternoon) | 9/16/2024 (PM) | 09/17/2024 |
Acceptance Test Inspection | Passed | 9/24/2024 (7:00 - 8:00) | 9/24/2024 (AM) | 09/26/2024 |
Fire Inspection Final | Passed | 10/30/2024 (10:00 - 12:00) | 10/30/2024 (AM) | 11/25/2024 |
Fire Inspection Final | Passed | 11/21/2024 (12:30 - 2:30) | 11/21/2024 (PM) | 11/25/2024 |