PRFS202405847
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Fire Inspection Final | Pending | |||
| Fire Rough-in Inspection | Pending | |||
| Fire Rough-in Inspection | Partial Pass | 9/9/2024 (10:00 - 12:00) | 9/9/2024 (AM) | 09/09/2024 |
| Hard lid areas ok to cover. | ||||
| Fire Rough-in Inspection | Partial Pass | 10/10/2024 (10:00 - 12:00) | 10/10/2024 (AM) | 10/10/2024 |
| Ok to cover phase II hard lid areas. | ||||
| Fire Rough-in Inspection | Partial Pass | 10/14/2024 (10:00 - 12:00) | 10/14/2024 (AM) | 10/14/2024 |
| Ok to cover west hard-lid area | ||||
| Hydro Test Start | Passed | 11/13/2024 (7:00 - 8:00) | 11/13/2024 (AM) | 11/13/2024 |
| 220 psi | ||||
| Hydro Test End | Passed | 11/13/2024 (8:00 - 10:00) | 11/13/2024 (AM) | 11/13/2024 |
| 220 psi | ||||
| Fire Rough-in Inspection | Partial Pass | 1/14/2025 | 01/14/2025 | |
| Approximately 17 painted cover plates throughout the space. Contractor to order new painted from manufacturer cover plates. | ||||
| Hydro Test End | Pending | 1/14/2025 (PM) | 01/14/2025 | |
| Ending psi 110 | ||||
| Hydro Test Start | Pending | 1/14/2025 (AM) | 01/14/2025 | |
| Starting psi 110 (50 over city). Contractor setup another hydro after adding additional heads. | ||||