PRFS202412235
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Partial Pass | 10/3/2024 (8:00 - 10:00) | 10/3/2024 (AM) | 10/04/2024 |
4th Floor complete | ||||
Fire Rough-in Inspection | Partial Pass | 10/04/2024 | ||
3rd floor up to 303 | ||||
Fire Rough-in Inspection | Partial Pass | 10/16/2024 (10:00 - 12:00) | 10/16/2024 (AM) | 10/16/2024 |
2nd floor completed | ||||
Fire Rough-in Inspection | Partial Pass | 10/28/2024 (8:00 - 10:00) | 10/28/2024 (AM) | 10/28/2024 |
1st floor units passed. | ||||
Fire Rough-in Inspection | Partial Pass | 11/19/2024 | ||
3rd floor west corner units, soffits ok to cover. | ||||
Hydro Test Start | Passed | 02/25/2025 | ||
Starting psi 206 | ||||
Hydro Test End | Passed | 02/25/2025 | ||
Ending psi 206 | ||||
Acceptance Test Inspection | Passed | 03/13/2025 | ||
Fire Inspection Final | Passed | 3/13/2025 (8:00 - 10:00) | 3/13/2025 (AM) | 03/13/2025 |