PRFS202503748
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Fire Inspection Final | Pending | |||
| Fire Rough-in Inspection | Pending | |||
| Hydro Test Start | Pending | |||
| Hydro Test End | Pending | |||
| Fire Rough-in Inspection | Partial Pass | 9/4/2025 (10:00 - 12:00) | 9/4/2025 (AM) | 09/04/2025 |
| west corridor, partial mezzanine, rink 3 locker rooms and under stadium stairs. | ||||
| Hydro Test Start | Partial Pass | 9/4/2025 (10:00 - 12:00) | 9/4/2025 (AM) | 09/04/2025 |
| Hydro of new pipe/north rink only. Starting psi 205 | ||||
| Hydro Test End | Partial Pass | 9/4/2025 (10:00 - 12:00) | 9/4/2025 (AM) | 09/04/2025 |
| Hydro of new pipe/north rink only. Ending psi 205 | ||||