PRMH201701944
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Passed | 3/31/2017 (8:00 - 10:00) | 3/31/2017 | 03/31/2017 |
Corrections:
Miscellaneous/Other
Comment Only
03/31/2017
Vav system West in space and room to east.
|
||||
Mechanical Rough-in Inspection | Passed | 4/25/2017 (8:00 - 10:00) | 4/25/2017 | 04/25/2017 |
Corrections:
Miscellaneous/Other
Comment Only
04/25/2017
Grease duct holding 1" w.c.
|
||||
Mechanical Final Inspection | Partial Pass | 4/27/2017 (12:30 - 2:30) | 4/27/2017 | 04/28/2017 |
Corrections:
Miscellaneous/Other
Comment Only
04/27/2017
General walkthrough of Pizza Villa main floor. Walked the grease duct up to the fourth floor. capture test done by Chad w baltec. Did not get on the roof.
|
||||
Mechanical Rough-in Inspection | VOID | 4/28/2017 (12:30 - 2:30) | 04/28/2017 | |
Mechanical Final Inspection | VOID | 4/4/2017 (8:00 - 10:00) | 4/4/2017 | 04/28/2017 |
Corrections:
Miscellaneous/Other
Comment Only
04/04/2017
West room vav and duct, easy room vav and duct. OK
|
||||
Mechanical Final Inspection | Passed | 4/28/2017 (12:30 - 2:30) | 4/28/2017 | 04/28/2017 |