PRMH201705532
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Partial Pass | 7/20/2017 (10:00 - 12:00) | 7/20/2017 | 07/20/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/20/2017
Duct from back to front, no vav box yet.
|
||||
Mechanical Rough-in Inspection | Passed | 7/25/2017 (12:30 - 2:30) | 7/25/2017 | 07/25/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/25/2017
Above ceiling duct and insulation.
|
||||
Mechanical Final Inspection | Passed | 8/10/2017 (10:00 - 12:00) | 8/10/2017 | 08/10/2017 |