Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Passed | 9/1/2017 (10:00 - 12:00) | 9/1/2017 | 09/01/2017 |
Corrections:
Miscellaneous/Other
Comment Only
09/01/2017
RI ok. Call for piping final and duct final together.
|
||||
Mechanical Final Inspection | Passed w/ Conditions | 9/20/2017 (10:00 - 12:00) | 9/20/2017 | 09/20/2017 |
Balance report not completed ? | ||||
Corrections:
Miscellaneous/Other
Outstanding
09/20/2017
Final above ceiling. - A. Return air grills not installed at this time. Volumn dampers and sealed ductwork - yes. B. Shut offs, at above ceiling for individual HVAC units-yes. No one on site for above ceiling inspection.C. Balance report ? Large space.
|
||||
Mechanical Final Inspection | Passed | 9/28/2017 (8:00 - 10:00) | 9/28/2017 | 09/28/2017 |