Summary

PRMH201711699
Mechanical/HVAC
Finaled
FELCOR/CSS HOLDINGS SPE
Alteration/Remodel
Embassy Suites mechanical and hvac in cook-to-order area, pool area, fitness room, lobby/luggage area (based on attached scope of work). Only HVAC work (excludes gas piping, power wiring, engineering, structural work, roofing orf equipment screening, fire suppression). Applicant only had "see plans" in description of work.
12/08/2017
01/03/2018
04/17/2019
10/19/2018

Locations

Permits

Permit Number: PRMH201711699

Mechanical
Finaled
01/03/2018
04/17/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Rough-in Inspection Partial Pass 2/26/2018 (10:00 - 12:00) 2/26/2018 02/26/2018
Corrections:


Miscellaneous/Other
Comment Only
02/26/2018
Exhaust ducting for bathrooms ok need one exhaust duct in family bathroom

Mechanical Rough-in Inspection Partial Pass 4/5/2018 (12:30 - 2:30) 4/5/2018 04/05/2018
Mechanical Rough-in Inspection Failed 5/1/2018 (8:00 - 10:00) 5/1/2018 05/01/2018
Corrections:


Miscellaneous/Other
Comment Only
05/01/2018
Grease duct air test was 0 " of water column

Mechanical Rough-in Inspection Partial Pass 5/8/2018 (8:00 - 10:00) 5/8/2018 05/08/2018
Corrections:


Miscellaneous/Other
Comment Only
05/08/2018
Pressure test on grease duct ok ri on duct in kitchen sealed

Mechanical Rough-in Inspection Partial Pass 5/30/2018 (8:00 - 10:00) 5/30/2018 05/30/2018
Corrections:


Miscellaneous/Other
Comment Only
05/30/2018
Light test of grease duct ok to insulate

Mechanical Final Inspection Partial Pass 6/13/2018 (10:00 - 12:00) 6/13/2018 06/13/2018
Corrections:


Miscellaneous/Other
Comment Only
06/13/2018
Need to see when all appliances are in and do a capture test on hood

Mechanical Rough-in Inspection Passed 7/19/2018 (12:30 - 2:30) 7/19/2018 07/19/2018
Corrections:


Miscellaneous/Other
Comment Only
07/19/2018
Capture test ok gas shut off to appliances fan shits down on alarm need kitchen and smoke Evan test done

Mechanical Rough-in Inspection VOID 7/19/2018 (12:30 - 2:30) 7/19/2018 07/23/2018
Canceled the ansul test same day - moved out a few days. Contacted inspectors. ajacobson 07/17/2018 8:14 AM
Mechanical Final Inspection Partial Pass 9/12/2018 (2:30 - 3:30) 9/12/2018 09/13/2018
Corrections:


Miscellaneous/Other
Comment Only
09/13/2018
Split unit in garage area

Mechanical Final Inspection Passed 10/19/2018