Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Final Inspection | Pending | |||
Mechanical Rough-in Inspection | Partial Pass | 7/10/2018 (12:30 - 2:30) | 7/10/2018 (PM) | 07/11/2018 |
Mechanical Rough-in Inspection | Partial Pass | 07/11/2018 | ||
Mechanical Rough-in Inspection | Partial Pass | 7/16/2018 (12:30 - 2:30) | 7/16/2018 | 07/16/2018 |
Corrections:
Miscellaneous/Other
Comment Only
07/16/2018
All gas piping to new boilers on roof and venting from boilers ok
|
||||
Mechanical Rough-in Inspection | Passed | 7/27/2018 (10:00 - 12:00) | 7/27/2018 | 07/27/2018 |
Corrections:
Miscellaneous/Other
Comment Only
07/27/2018
All 6” chilled water hot water to cafe all holding 90psi
|
||||
Mechanical Rough-in Inspection | Partial Pass | 8/1/2018 (Afternoon) | 8/1/2018 | 08/02/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/02/2018
90 psi on all cw and hw piping
|
||||
Mechanical Rough-in Inspection | Partial Pass | 8/6/2018 (10:00 - 12:00) | 8/6/2018 (AM) | 08/06/2018 |
Mechanical Rough-in Inspection | Partial Pass | 8/14/2018 (10:00 - 12:00) | 8/14/2018 | 08/14/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/14/2018
Pressure test on hot water piping
|
||||
Mechanical Rough-in Inspection | Partial Pass | 8/16/2018 (Morning) | 8/16/2018 | 08/16/2018 |
Corrections:
Miscellaneous/Other
Outstanding
08/16/2018
Chilled water air test 90 psi see paper work for area
|
||||
Mechanical Rough-in Inspection | Partial Pass | 8/20/2018 (8:00 - 10:00) | 8/20/2018 | 08/21/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/21/2018
Duct serving the gym area and new return duct need grills installed and balanced
|
||||
Mechanical Rough-in Inspection | Passed | 8/22/2018 (10:00 - 12:00) | 8/22/2018 | 08/22/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/22/2018
See paperwork
|
||||
Mechanical Rough-in Inspection | Passed | 8/23/2018 (10:00 - 12:00) | 8/23/2018 | 08/23/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/23/2018
All air test are completed and performed to as on the specs
|
||||
Mechanical Final Inspection | Partial Pass | 8/30/2018 (12:30 - 2:30) | 8/30/2018 | 09/04/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/04/2018
All duct and piping complete need commissioning report
|
||||