PRMH201806319
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Passed | 6/26/2018 (8:00 - 10:00) | 6/26/2018 | 06/26/2018 |
Corrections:
Miscellaneous/Other
Comment Only
06/26/2018
Duct in cafeteria. Ok. See plan for area where work done.
|
||||
Above Ceiling Inspection | Passed | 8/9/2018 (8:00 - 10:00) | 8/9/2018 | 08/09/2018 |
Corrections:
Miscellaneous/Other
Comment Only
08/09/2018
All duct wrapped ok to pad out need a balance report and commissioning report if required
|
||||
Mechanical Final Inspection | Passed | 08/30/2018 |