PRMH201808924
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Rough-in Inspection | Passed | 8/22/2018 (8:00 - 10:00) | 8/22/2018 | 08/22/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/22/2018
Men's bathroom, pantry on North side. East conference area. Above ceiling ok
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 9/6/2018 (12:30 - 2:30) | 9/6/2018 | 09/07/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/07/2018
Need to see damper actuation and test smoke detectors if tied in to system
|
||||
| Mechanical Final Inspection | Failed | 9/24/2018 (12:30 - 2:30) | 9/24/2018 | 09/24/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/24/2018
Need fire dampers to actuate finish installing duct figure out controls on heat pumps
|
||||
| Mechanical Final Inspection | Passed | 10/30/2018 (8:00 - 10:00) | 10/30/2018 (AM) | 10/30/2018 |