PRMH201809937
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Rough-in Inspection | Partial Pass | 10/11/2019 (8:00 - 10:00) | 10/11/2019 (AM) | 10/11/2019 |
| Mechanical Rough-in Inspection | Partial Pass | 10/15/2019 (8:00 - 10:00) | 10/15/2019 (AM) | 10/15/2019 |
| Mechanical Rough-in Inspection | Partial Pass | 10/18/2019 (10:00 - 12:00) | 10/18/2019 (AM) | 10/18/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/18/2019
Gas pressure test ok
|
||||
| Mechanical Rough-in Inspection | Failed | 10/22/2019 (10:00 - 12:00) | 10/22/2019 (AM) | 10/22/2019 |
| Mechanical Rough-in Inspection | Failed | 10/25/2019 (10:00 - 12:00) | 10/25/2019 (AM) | 10/25/2019 |
| Mechanical Rough-in Inspection | Passed | 10/29/2019 (10:00 - 12:00) | 10/29/2019 (AM) | 10/29/2019 |
| Mechanical Rough-in Inspection | Partial Pass | 11/6/2019 (12:30 - 2:30) | 11/6/2019 (PM) | 11/06/2019 |
|
Corrections:
Miscellaneous/Other
Carried Forward
11/08/2019
Fire angles installed at each job location at floor to be addressed. The angles that are in place do not cover the floor opening.Fire caulk at corners where angles meet, and any openings of electrical work angles are cut out.
|
||||
|
Miscellaneous/Other
Comment Only
11/06/2019
Fuse-a-ble dampers at each floor duct location approved.
See “outstanding” comment for correction.
|
||||
| Mechanical Rough-in Inspection | Failed | 11/8/2019 (10:00 - 12:00) | 11/8/2019 (AM) | 11/08/2019 |
| Mechanical Final Inspection | Partial Pass | 11/13/2019 (8:00 - 10:00) | 11/13/2019 (AM) | 11/13/2019 |
|
Corrections:
Miscellaneous/Other
Carried Forward
11/13/2019
Fire angles installed at each job location at floor to be addressed. The angles that are in place do not cover the floor opening.Fire caulk at corners where angles meet, and any openings of electrical work angles are cut out.
|
||||
| Mechanical Final Inspection | Passed | 12/2/2019 (10:00 - 12:00) | 12/2/2019 (AM) | 12/02/2019 |
| Mechanical Final Inspection | Passed | 12/6/2019 (10:00 - 12:00) | 12/6/2019 (AM) | 12/06/2019 |
|
Corrections:
Miscellaneous/Other
Outstanding
11/13/2019
Fire angles installed at each job location at floor to be addressed. The angles that are in place do not cover the floor opening.Fire caulk at corners where angles meet, and any openings of electrical work angles are cut out.
|
||||