PRMH201810098
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Partial Pass | 9/26/2018 (8:00 - 10:00) | 9/26/2018 | 09/26/2018 |
Corrections:
Miscellaneous/Other
Comment Only
09/26/2018
Phase 1 duct over storage unit
|
||||
Mechanical Rough-in Inspection | Partial Pass | 11/6/2018 (10:00 - 12:00) | 11/6/2018 (AM) | 11/06/2018 |
Mechanical Final Inspection | Passed | 1/16/2019 (10:00 - 12:00) | 1/16/2019 (AM) | 01/16/2019 |