Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Partial Pass | 2/21/2019 (12:30 - 2:30) | 2/21/2019 (PM) | 02/21/2019 |
No rough in above ceiling was called in or requested. Work performed, and ceiling tiles installed. Two existing bathroom exhaust, extend existing ductwork, and move diffusers, and I return air installed. Balance system, with balancing report. Contractor on site. | ||||
Mechanical Final Inspection | Passed | 2/21/2019 (12:30 - 2:30) | 2/21/2019 (PM) | 02/21/2019 |
Area of work. A. Small north east front of store area near the public restrooms. Remodel existing back house secured (employee sink-refrigerator area.) Gilbert Mechanical extended the existing main floor galvanized horizontal duct above ceiling 8x16, feeding 4 new supply difussers, and adding one additional above ceiling ducted return air. B. Balancing report provided by Gilbert Mechanical, to be e mailed to Brian Post-General Inspector. C. Contractor on site with various ceiling tile removed, for inspector. |