Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Passed | 2/25/2019 (8:00 - 10:00) | 2/25/2019 (AM) | 02/25/2019 |
Corrections:
Miscellaneous/Other
Comment Only
02/25/2019
RI ok to cover
|
||||
Mechanical Final Inspection | Passed | 3/11/2019 (10:00 - 12:00) | 3/11/2019 (AM) | 03/11/2019 |
Corrections:
Miscellaneous/Other
Comment Only
03/11/2019
Rough in ok need to see all diffusers installed and balance report
|