PRMH201901342


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRMH201901342
Mechanical/HVAC
Finaled
BCS3 HOUSING LLC
Other
402 unit apartments, and 6 level of semi -enclosed parking garage, 6 stories.
02/13/2019
04/22/2019
01/18/2021
07/22/2020

Locations

Permits

Permit Number: PRMH201901342

Mechanical
Finaled
04/22/2019
01/18/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Rough-in Inspection Partial Pass 6/4/2019 (12:30 - 2:30) 6/4/2019 (PM) 06/04/2019
Mechanical Rough-in Inspection Partial Pass 7/25/2019 (10:00 - 12:00) 7/25/2019 (AM) 07/25/2019
Mechanical Rough-in Inspection Partial Pass 8/12/2019 (12:30 - 2:30) 8/12/2019 (PM) 08/12/2019
Mechanical Rough-in Inspection Partial Pass 9/10/2019 (8:00 - 10:00) 9/10/2019 (AM) 09/10/2019
Mechanical Rough-in Inspection Partial Pass 9/12/2019 (10:00 - 12:00) 9/12/2019 (AM) 09/12/2019
Mechanical Rough-in Inspection Partial Pass 9/17/2019 (10:00 - 12:00) 9/17/2019 (AM) 09/17/2019
Mechanical Rough-in Inspection Partial Pass 9/19/2019 (10:00 - 12:00) 9/19/2019 (AM) 09/19/2019
Mechanical Rough-in Inspection Partial Pass 9/26/2019 (10:00 - 12:00) 9/26/2019 (AM) 09/26/2019
Mechanical Rough-in Inspection Partial Pass 9/30/2019 (7:00 - 8:00) 9/30/2019 (AM) 09/30/2019
Mechanical Rough-in Inspection Partial Pass 10/1/2019 (7:00 - 8:00) 10/1/2019 (AM) 10/01/2019
Mechanical Rough-in Inspection Partial Pass 10/2/2019 (7:00 - 8:00) 10/2/2019 (AM) 10/02/2019
Mechanical Rough-in Inspection Partial Pass 10/8/2019 (8:00 - 10:00) 10/8/2019 (AM) 10/08/2019
Mechanical Rough-in Inspection Partial Pass 10/9/2019 (7:00 - 8:00) 10/9/2019 (AM) 10/09/2019
Mechanical Air Test Inspection Partial Pass 10/9/2019 (8:00 - 10:00) 10/9/2019 (AM) 10/09/2019
Mechanical Rough-in Inspection Partial Pass 10/9/2019 (10:00 - 12:00) 10/9/2019 (AM) 10/09/2019
Mechanical Rough-in Inspection Partial Pass 10/10/2019 (7:00 - 8:00) 10/10/2019 (AM) 10/10/2019
Mechanical Rough-in Inspection Partial Pass 10/11/2019 (7:00 - 8:00) 10/11/2019 (AM) 10/11/2019
Mechanical Rough-in Inspection Partial Pass 10/14/2019 (12:30 - 2:30) 10/14/2019 (PM) 10/14/2019
Mechanical Rough-in Inspection Partial Pass 10/15/2019 (10:00 - 12:00) 10/15/2019 (AM) 10/15/2019
Mechanical Rough-in Inspection Partial Pass 10/18/2019 (8:00 - 10:00) 10/18/2019 (AM) 10/18/2019
Corrections:


Miscellaneous/Other
Comment Only
10/18/2019
4th sw soffits ok

Mechanical Rough-in Inspection Partial Pass 10/22/2019 (8:00 - 10:00) 10/22/2019 (AM) 10/22/2019
Mechanical Rough-in Inspection Partial Pass 10/23/2019 (8:00 - 10:00) 10/23/2019 (AM) 10/23/2019
Corrections:


Miscellaneous/Other
Comment Only
10/23/2019
5th floor nw RI

Mechanical Rough-in Inspection Partial Pass 10/24/2019 (10:00 - 12:00) 10/24/2019 (AM) 10/24/2019
Mechanical Rough-in Inspection Partial Pass 10/25/2019 (8:00 - 10:00) 10/25/2019 (AM) 10/25/2019
Mechanical Rough-in Inspection Partial Pass 11/4/2019 (8:00 - 10:00) 11/4/2019 (AM) 11/04/2019
Corrections:


Miscellaneous/Other
Comment Only
11/04/2019
2nd floor of SW building, area 1... ducting at soffit. Approved

Mechanical Rough-in Inspection Partial Pass 11/06/2019
Corrections:


Miscellaneous/Other
Comment Only
11/06/2019
SW building, second floor unit ducting areas 1&2... approved

Mechanical Rough-in Inspection Partial Pass 11/8/2019 (10:00 - 12:00) 11/8/2019 (AM) 11/08/2019
Mechanical Rough-in Inspection Partial Pass 11/12/2019 (8:00 - 10:00) 11/12/2019 (AM) 11/12/2019
Mechanical Rough-in Inspection Partial Pass 11/15/2019 (8:00 - 10:00) 11/15/2019 (AM) 11/15/2019
Mechanical Rough-in Inspection Partial Pass 11/21/2019 (10:00 - 12:00) 11/21/2019 (AM) 11/21/2019
Mechanical Rough-in Inspection Partial Pass 11/25/2019 (8:00 - 10:00) 11/25/2019 (AM) 11/25/2019
Mechanical Rough-in Inspection Partial Pass 11/27/2019 (8:00 - 10:00) 11/27/2019 (AM) 11/27/2019
Mechanical Rough-in Inspection Partial Pass 12/6/2019 (8:00 - 10:00) 12/6/2019 (AM) 12/09/2019
Mechanical Rough-in Inspection Partial Pass 12/10/2019 (8:00 - 10:00) 12/10/2019 (AM) 12/10/2019
Mechanical Rough-in Inspection Partial Pass 12/12/2019 (8:00 - 10:00) 12/12/2019 (AM) 12/12/2019
Mechanical Rough-in Inspection Partial Pass 12/17/2019 (8:00 - 10:00) 12/17/2019 (AM) 12/17/2019
Mechanical Rough-in Inspection Partial Pass 12/30/2019 (8:00 - 10:00) 12/30/2019 (AM) 12/30/2019
Mechanical Rough-in Inspection Partial Pass 1/2/2020 (8:00 - 10:00) 1/2/2020 (AM) 01/02/2020
Mechanical Rough-in Inspection Partial Pass 1/7/2020 (8:00 - 10:00) 1/7/2020 (AM) 01/07/2020
Mechanical Rough-in Inspection Partial Pass 1/13/2020 (8:00 - 10:00) 1/13/2020 (AM) 01/13/2020
Mechanical Rough-in Inspection Partial Pass 1/16/2020 (8:00 - 10:00) 1/16/2020 (AM) 01/16/2020
Mechanical Rough-in Inspection Partial Pass 1/21/2020 (10:00 - 12:00) 1/21/2020 (AM) 01/21/2020
Mechanical Rough-in Inspection Partial Pass 1/23/2020 (8:00 - 10:00) 1/23/2020 (AM) 01/23/2020
Mechanical Rough-in Inspection Partial Pass 1/27/2020 (8:00 - 10:00) 1/27/2020 (AM) 01/27/2020
Mechanical Rough-in Inspection Partial Pass 1/30/2020 (8:00 - 10:00) 1/30/2020 (AM) 01/30/2020
Mechanical Rough-in Inspection Partial Pass 2/3/2020 (8:00 - 10:00) 2/3/2020 (AM) 02/03/2020
Mechanical Rough-in Inspection Partial Pass 2/5/2020 (8:00 - 10:00) 2/5/2020 (AM) 02/05/2020
Mechanical Rough-in Inspection Partial Pass 2/10/2020 (8:00 - 10:00) 2/10/2020 (AM) 02/10/2020
Mechanical Rough-in Inspection Passed 2/12/2020 (8:00 - 10:00) 2/12/2020 (AM) 02/12/2020
Mechanical Rough-in Inspection Partial Pass 2/18/2020 (8:00 - 10:00) 2/18/2020 (AM) 02/18/2020
Mechanical Rough-in Inspection Partial Pass 2/20/2020 (8:00 - 10:00) 2/20/2020 (AM) 02/20/2020
Mechanical Rough-in Inspection Passed 3/9/2020 (10:00 - 12:00) 3/9/2020 (AM) 03/09/2020
Mechanical Rough-in Inspection Partial Pass 3/11/2020 (10:00 - 12:00) 3/11/2020 (AM) 03/11/2020
Mechanical Rough-in Inspection Partial Pass 3/13/2020 (10:00 - 12:00) 3/13/2020 (AM) 03/13/2020
Mechanical Rough-in Inspection Partial Pass 3/16/2020 (10:00 - 12:00) 3/16/2020 (AM) 03/16/2020
Corrections:


Miscellaneous/Other
Comment Only
03/16/2020
1st floor ductwork ok residential rooms

Mechanical Rough-in Inspection Partial Pass 3/18/2020 (10:00 - 12:00) 3/18/2020 (AM) 03/18/2020
Corrections:


Miscellaneous/Other
Comment Only
03/18/2020
Ducting rough in at area 7 units approved

Mechanical Rough-in Inspection Partial Pass 3/20/2020 (8:00 - 10:00) 3/20/2020 (AM) 03/20/2020
Corrections:


Miscellaneous/Other
Comment Only
03/20/2020
Ducting installation in sump room... approved.

Mechanical Rough-in Inspection Partial Pass 3/23/2020 (10:00 - 12:00) 3/23/2020 (AM) 03/23/2020
Corrections:


Miscellaneous/Other
Comment Only
03/23/2020
Area 1through 4 from 6th floor to 4th floor units are final

Mechanical Rough-in Inspection Partial Pass 3/25/2020 (10:00 - 12:00) 3/25/2020 (AM) 03/26/2020
Mechanical Rough-in Inspection Partial Pass 3/27/2020 (10:00 - 12:00) 3/27/2020 (AM) 03/27/2020
Mechanical Rough-in Inspection Partial Pass 3/30/2020 (10:00 - 12:00) 3/30/2020 (AM) 03/30/2020
Mechanical Rough-in Inspection Partial Pass 4/1/2020 (10:00 - 12:00) 4/1/2020 (AM) 04/01/2020
Mechanical Rough-in Inspection Partial Pass 4/3/2020 (10:00 - 12:00) 4/3/2020 (AM) 04/03/2020
Mechanical Rough-in Inspection Partial Pass 4/6/2020 (10:00 - 12:00) 4/6/2020 (AM) 04/06/2020
Mechanical Rough-in Inspection Passed 4/8/2020 (10:00 - 12:00) 4/8/2020 (AM) 04/08/2020
Mechanical Rough-in Inspection Passed 4/10/2020 (10:00 - 12:00) 4/10/2020 (AM) 04/10/2020
Mechanical Rough-in Inspection Partial Pass 4/14/2020 (10:00 - 12:00) 4/14/2020 (AM) 04/14/2020
Mechanical Rough-in Inspection Partial Pass 4/16/2020 (10:00 - 12:00) 4/16/2020 (AM) 04/16/2020
Mechanical Rough-in Inspection Passed 4/21/2020 (10:00 - 12:00) 4/21/2020 (AM) 04/21/2020
Mechanical Rough-in Inspection Passed 4/23/2020 (10:00 - 12:00) 4/23/2020 (AM) 04/23/2020
Mechanical Rough-in Inspection Passed 4/28/2020 (10:00 - 12:00) 4/28/2020 (AM) 04/28/2020
Mechanical Rough-in Inspection Partial Pass 4/30/2020 (10:00 - 12:00) 4/30/2020 (AM) 04/30/2020
Corrections:


Miscellaneous/Other
Comment Only
04/30/2020
6th floor in area 6 ok

Mechanical Rough-in Inspection Partial Pass 5/7/2020 (10:00 - 12:00) 5/7/2020 (AM) 05/07/2020
Corrections:


Miscellaneous/Other
Comment Only
05/07/2020
Floors 5 and 4 in area 6 ok

Mechanical Rough-in Inspection Partial Pass 5/12/2020 (10:00 - 12:00) 5/12/2020 (AM) 05/12/2020
Mechanical Rough-in Inspection Partial Pass 5/14/2020 (10:00 - 12:00) 5/14/2020 (AM) 05/14/2020
Mechanical Rough-in Inspection Partial Pass 5/19/2020 (10:00 - 12:00) 5/19/2020 (AM) 05/19/2020
Mechanical Rough-in Inspection Partial Pass 5/21/2020 (10:00 - 12:00) 5/21/2020 (AM) 05/21/2020
Mechanical Rough-in Inspection Partial Pass 5/26/2020 (10:00 - 12:00) 5/26/2020 (AM) 05/26/2020
Mechanical Rough-in Inspection Partial Pass 5/28/2020 (10:00 - 12:00) 5/28/2020 (AM) 05/28/2020
Mechanical Rough-in Inspection Partial Pass 6/2/2020 (10:00 - 12:00) 6/2/2020 (AM) 06/02/2020
Corrections:


Miscellaneous/Other
Outstanding
06/02/2020
6th floor area 7

Mechanical Rough-in Inspection Passed 6/4/2020 (10:00 - 12:00) 6/4/2020 (AM) 06/04/2020
Corrections:


Miscellaneous/Other
Comment Only
06/04/2020
5th floor area 7 good

Mechanical Rough-in Inspection Partial Pass 6/9/2020 (10:00 - 12:00) 6/9/2020 (AM) 06/09/2020
Corrections:


Miscellaneous/Other
Comment Only
06/09/2020
Fire smoke dampers in area 7 ok

Mechanical Rough-in Inspection Passed 6/11/2020 (10:00 - 12:00) 6/11/2020 (AM) 06/11/2020
Mechanical Rough-in Inspection Passed 7/1/2020 (10:00 - 12:00) 7/1/2020 (AM) 07/01/2020
Corrections:


Miscellaneous/Other
Comment Only
07/01/2020
First floor area 7

Mechanical Rough-in Inspection Passed 7/2/2020 (10:00 - 12:00) 7/2/2020 (AM) 07/06/2020
Mechanical Final Inspection Passed 6/29/2020 (12:30 - 2:30) 6/29/2020 (PM) 07/22/2020
Corrections:


Miscellaneous/Other
Comment Only
06/29/2020
2nd floor area 6

Mechanical Air Test Inspection Passed 07/22/2020
Mechanical Final Inspection Passed 07/22/2020