Permit Application Status

PRMH201902715


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRMH201902715
Mechanical/HVAC
Finaled
CAPP INDUSTRIES INCORPORATED
Alteration/Repair/Replace
Remove gas lines for re-roof project. Reconnect back up with new supports, replace gas pipe where needed. Raise exhaust fans and condensers where needed for re-roof project.
03/28/2019
03/21/2019
09/17/2019
01/07/2020

Locations

Permits

Permit Number: PRMH201902715

Mechanical
Finaled
03/21/2019
09/17/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Final Inspection Not Ready 12/5/2019 (8:00 - 10:00) 12/5/2019 (AM) 12/05/2019
Mechanical Final Inspection Passed 1/7/2020 (10:00 - 12:00) 1/7/2020 (AM) 01/07/2020