PRMH201904308
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Not Ready | 5/10/2019 (10:00 - 12:00) | 5/10/2019 (AM) | 05/10/2019 |
Mechanical Final Inspection | Not Ready | 5/10/2019 (10:00 - 12:00) | 5/10/2019 (AM) | 05/10/2019 |
Mechanical Rough-in Inspection | Partial Pass | 5/14/2019 (12:30 - 2:30) | 5/14/2019 (PM) | 05/14/2019 |
Mechanical Final Inspection | Not Ready | 5/14/2019 (2:30 - 3:30) | 5/14/2019 (PM) | 05/14/2019 |
Mechanical Rough-in Inspection | Passed | 5/28/2019 (10:00 - 12:00) | 5/28/2019 (AM) | 05/28/2019 |
Corrections:
Miscellaneous/Other
Comment Only
05/28/2019
Need to see fire damper operation on final
|
||||
Mechanical Final Inspection | Failed | 6/25/2019 (10:00 - 12:00) | 6/25/2019 (AM) | 06/25/2019 |
Corrections:
Miscellaneous/Other
Comment Only
06/25/2019
Need to see damper operation and smoke detectors
|
||||
Mechanical Final Inspection | Failed | 6/27/2019 (10:00 - 12:00) | 6/27/2019 (AM) | 06/27/2019 |
Corrections:
Miscellaneous/Other
Comment Only
06/27/2019
Locked no one there
|
||||
Mechanical Final Inspection | Failed | 7/1/2019 (2:30 - 3:30) | 7/1/2019 (PM) | 07/01/2019 |
Mechanical Final Inspection | Partial Pass | 8/19/2019 (12:30 - 2:30) | 8/19/2019 (PM) | 08/19/2019 |
Corrections:
Miscellaneous/Other
Comment Only
08/19/2019
fire damper operational framing around dampers not approved
|
||||
Mechanical Final Inspection | Failed | 10/8/2019 (12:30 - 2:30) | 10/8/2019 (PM) | 10/08/2019 |
Mechanical Final Inspection | Partial Pass | 10/14/2019 (12:30 - 2:30) | 10/14/2019 (PM) | 10/14/2019 |
Mechanical Final Inspection | Passed | 10/21/2019 (12:30 - 2:30) | 10/21/2019 (PM) | 10/21/2019 |