PRMH201910301
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Partial Pass | 11/12/2019 (8:00 - 10:00) | 11/12/2019 (AM) | 11/12/2019 |
Mechanical Rough-in Inspection | Partial Pass | 1/13/2020 (8:00 - 10:00) | 1/13/2020 (AM) | 01/13/2020 |
Mechanical Rough-in Inspection | Partial Pass | 2/4/2020 (12:30 - 2:30) | 2/4/2020 (PM) | 02/04/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/04/2020
Viewed ducting supplies and returns with dampers at floor located in the shafts. Installation approved
|
||||
Mechanical Rough-in Inspection | Partial Pass | 02/14/2020 | ||
Progress - 2nd level concrete floor openings for 1 hr rated mechanical shafts containing supply ducting and the gypsum plenum mechanical shaft for non ducted return air. 1 hr rated shafts. A. Progress on enclosing gap space at concrete floor openings and mechanical supply galvanized ductwork. B. Six locations per 2nd floor mechanical plan. C. Ongoing inspections. | ||||
Mechanical Final Inspection | Partial Pass | 4/6/2020 (8:00 - 10:00) | 4/6/2020 (AM) | 04/06/2020 |
Mechanical Final Inspection | Partial Pass | 4/17/2020 (8:00 - 10:00) | 4/17/2020 (AM) | 04/17/2020 |
Mechanical Final Inspection | Passed | 5/1/2020 (8:00 - 10:00) | 5/1/2020 (AM) | 05/01/2020 |