PRMH201910966
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Rough-in Inspection | Pending | |||
| Mechanical Final Inspection | Pending | |||
| Mechanical Rough-in Inspection | Partial Pass | 5/18/2020 (10:00 - 12:00) | 5/18/2020 (AM) | 05/18/2020 |
| Mechanical Rough-in Inspection | Partial Pass | 5/27/2020 (10:00 - 12:00) | 5/27/2020 (AM) | 05/27/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/27/2020
4th floor east rough in
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 5/28/2020 (8:00 - 10:00) | 5/28/2020 (AM) | 05/28/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/28/2020
Soffit for model room
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 6/9/2020 (10:00 - 12:00) | 6/9/2020 (AM) | 06/09/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/09/2020
4th floor west tower ri ok need transfers to rooms with dryers
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 6/10/2020 (8:00 - 10:00) | 6/10/2020 (AM) | 06/10/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/10/2020
3rd floor rough in east tower
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 6/23/2020 (10:00 - 12:00) | 6/23/2020 (AM) | 06/23/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/23/2020
3rd floor soffits on east building
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 6/24/2020 (12:30 - 2:30) | 6/24/2020 (PM) | 06/24/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/24/2020
3rd floor ri on west ok
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/1/2020 (12:30 - 2:30) | 7/1/2020 (PM) | 07/01/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/01/2020
4th floor soffits west and 2nd floor east rough in
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/7/2020 (2:30 - 3:30) | 7/7/2020 (PM) | 07/07/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/07/2020
2nd floor west and first floor east rough in ok
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/9/2020 (10:00 - 12:00) | 7/9/2020 (AM) | 07/09/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/09/2020
3rd floor east soffits and first floor east ri ok
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/16/2020 (10:00 - 12:00) | 7/16/2020 (AM) | 07/16/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/16/2020
2nd floor east soffit 3rd floor soffit west and first floor west rough in
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/28/2020 (10:00 - 12:00) | 7/28/2020 (AM) | 07/28/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/28/2020
North en first floor
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 8/10/2020 (10:00 - 12:00) | 8/10/2020 (AM) | 08/10/2020 |
| Soffit Ducts - 2nd Floor | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
08/10/2020
Second floor soffits west side
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 8/11/2020 (8:00 - 10:00) | 8/11/2020 (AM) | 08/11/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/11/2020
Fans for fitness and yoga area
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 9/1/2020 (10:00 - 12:00) | 9/1/2020 (AM) | 09/01/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/01/2020
All four shafts are ok to close up
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 9/2/2020 (10:00 - 12:00) | 9/2/2020 (AM) | 09/02/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/02/2020
4th floor rough ins on w st building
|
||||
| Mechanical Rough-in Inspection | Passed | 9/3/2020 (12:30 - 2:30) | 9/3/2020 (PM) | 09/03/2020 |
| Mechanical Rough-in Inspection | Partial Pass | 9/9/2020 (10:00 - 12:00) | 9/9/2020 (AM) | 09/09/2020 |
| Mechanical Rough-in Inspection | Passed | 9/15/2020 (10:00 - 12:00) | 9/15/2020 (AM) | 09/15/2020 |
| Mechanical Final Inspection | Partial Pass | 9/24/2020 (8:00 - 10:00) | 9/24/2020 (AM) | 09/24/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/24/2020
4th floor soffits and common area in first building
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 9/30/2020 (10:00 - 12:00) | 9/30/2020 (AM) | 09/30/2020 |
| Mechanical Rough-in Inspection | Partial Pass | 10/1/2020 (10:00 - 12:00) | 10/1/2020 (AM) | 10/01/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/01/2020
4th floor east soffits done
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 10/9/2020 (10:00 - 12:00) | 10/9/2020 (AM) | 10/09/2020 |
| Mechanical Rough-in Inspection | Partial Pass | 10/14/2020 | 10/14/2020 (AM) | 10/14/2020 |
| Mechanical Rough-in Inspection | Partial Pass | 10/19/2020 (8:00 - 10:00) | 10/19/2020 (AM) | 10/19/2020 |
| Soffit Duct | ||||
| Mechanical Rough-in Inspection | Partial Pass | 10/28/2020 (12:30 - 2:30) | 10/28/2020 (PM) | 10/29/2020 |
| Mechanical Rough-in Inspection | Partial Pass | 10/29/2020 (8:00 - 10:00) | 10/29/2020 (AM) | 10/29/2020 |
| Mechanical Rough-in Inspection | Partial Pass | 11/4/2020 (8:00 - 10:00) | 11/4/2020 (AM) | 11/04/2020 |
| Mechanical Rough-in Inspection | Passed | 11/19/2020 (10:00 - 12:00) | 11/19/2020 (AM) | 11/19/2020 |
| Mechanical Rough-in Inspection | Partial Pass | 11/24/2020 (10:00 - 12:00) | 11/24/2020 (AM) | 11/24/2020 |
| Mechanical Rough-in Inspection | Partial Pass | 12/7/2020 (8:00 - 10:00) | 12/7/2020 (AM) | 12/07/2020 |
| Mechanical Rough-in Inspection | Partial Pass | 12/14/2020 (2:30 - 3:30) | 12/14/2020 (PM) | 12/14/2020 |
| Mechanical Final Inspection | Partial Pass | 12/16/2020 (8:00 - 10:00) | 12/16/2020 (AM) | 12/16/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/16/2020
3rd and 4th floors final on east building
|
||||
| Mechanical Final Inspection | Partial Pass | 12/29/2020 (10:00 - 12:00) | 12/29/2020 (AM) | 12/29/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/29/2020
2nd and 1st floor room finals in east building
|
||||
| Mechanical Final Inspection | Partial Pass | 1/4/2021 (12:30 - 2:30) | 1/4/2021 (PM) | 01/04/2021 |
| Mechanical Final Inspection | Partial Pass | 1/19/2021 (10:00 - 12:00) | 1/19/2021 (AM) | 01/19/2021 |
| Mechanical Final Inspection | Partial Pass | 1/25/2021 (10:00 - 12:00) | 1/25/2021 (AM) | 01/25/2021 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/25/2021
Tested all fire/smoke dampers operation
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 2/17/2021 (12:30 - 2:30) | 2/17/2021 (PM) | 02/17/2021 |
| Mechanical Rough-in Inspection | Partial Pass | 2/24/2021 (10:00 - 12:00) | 2/24/2021 (AM) | 02/24/2021 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/24/2021
Air test holding on gas lines for common corridor, common rooms, water heat, and outdoor grills and fire pits... approved.
|
||||
|
Miscellaneous/Other
Comment Only
02/24/2021
Air test holding on gas lines for common corridor, common rooms, water heat, and outdoor grills and fire pits... approved.
|
||||
| Mechanical Final Inspection | Partial Pass | 3/10/2021 (10:00 - 12:00) | 3/10/2021 (AM) | 03/10/2021 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/10/2021
3rd and 4th floors room finals in west building
|
||||
| Mechanical Final Inspection | Partial Pass | 3/17/2021 (10:00 - 12:00) | 3/17/2021 (AM) | 03/17/2021 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/17/2021
2nd floor finals good have some on 1st to complete
|
||||
| Mechanical Final Inspection | Partial Pass | 4/13/2021 (8:00 - 10:00) | 4/13/2021 (AM) | 04/13/2021 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/13/2021
All rooms are finales need to fire smoke dampers and garage start ups
|
||||
| Mechanical Final Inspection | Failed | 4/21/2021 (10:00 - 12:00) | 4/21/2021 (AM) | 04/21/2021 |
| Mechanical Final Inspection | Partial Pass | 5/5/2021 (8:00 - 10:00) | 5/5/2021 (AM) | 05/05/2021 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/05/2021
Need balance report and start up on make up air
|
||||