PRMH201912238
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Partial Pass | 6/22/2020 (12:30 - 2:30) | 6/22/2020 (PM) | 06/22/2020 |
Mechanical Rough-in Inspection | Partial Pass | 8/14/2020 (10:00 - 12:00) | 8/14/2020 (AM) | 08/14/2020 |
Mechanical Rough-in Inspection | Partial Pass | 9/2/2020 (8:00 - 10:00) | 9/2/2020 (AM) | 09/02/2020 |
Corrections:
Miscellaneous/Other
Comment Only
09/02/2020
Gas to generator
|
||||
Mechanical Rough-in Inspection | Partial Pass | 9/11/2020 (12:30 - 2:30) | 9/11/2020 (PM) | 09/11/2020 |
Corrections:
Miscellaneous/Other
Comment Only
09/11/2020
3rd floor above ceiling in memory care unit
|
||||
Mechanical Rough-in Inspection | Partial Pass | 9/17/2020 (10:00 - 12:00) | 9/17/2020 (AM) | 09/17/2020 |
Mechanical Rough-in Inspection | Partial Pass | 9/28/2020 (10:00 - 12:00) | 9/28/2020 (AM) | 09/28/2020 |
Mechanical Rough-in Inspection | Partial Pass | 10/20/2020 (8:00 - 10:00) | 10/20/2020 (AM) | 10/20/2020 |
Mechanical Rough-in Inspection | Partial Pass | 11/6/2020 (8:00 - 10:00) | 11/6/2020 (AM) | 11/06/2020 |
Mechanical Rough-in Inspection | Partial Pass | 11/20/2020 (10:00 - 12:00) | 11/20/2020 (AM) | 11/20/2020 |
Corrections:
Miscellaneous/Other
Comment Only
11/20/2020
100 psi on snow melt pex
|
||||
Mechanical Rough-in Inspection | Partial Pass | 12/9/2020 (12:30 - 2:30) | 12/9/2020 (PM) | 12/10/2020 |
Mechanical Rough-in Inspection | Partial Pass | 12/17/2020 (12:30 - 2:30) | 12/17/2020 (PM) | 12/17/2020 |
Mechanical Final Inspection | Partial Pass | 12/22/2020 (Afternoon) | 12/22/2020 (PM) | 12/22/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/22/2020
Tested smoke detectors and fire smoke dampers
|
||||
Mechanical Final Inspection | Partial Pass | 1/13/2021 (2:30 - 3:30) | 1/13/2021 (PM) | 01/13/2021 |
Corrections:
Miscellaneous/Other
Comment Only
01/13/2021
Smoke capture test hood on both kitchens
|
||||
Mechanical Final Inspection | Partial Pass | 1/28/2021 (12:30 - 2:30) | 1/28/2021 (PM) | 02/01/2021 |
Mechanical Final Inspection | Partial Pass | 11/1/2021 (8:00 - 10:00) | 11/1/2021 (AM) | 11/01/2021 |
West side, snow melt PEX system with air test on while pouring. Passed. (Ongoing work.) passed. | ||||
Corrections:
Miscellaneous/Other
Comment Only
11/01/2021
Rough in - west side, exterior PEX snow melt system with air test left on while pouring new insulated concrete entrance with trench drain.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 12/1/2021 (10:00 - 12:00) | 12/1/2021 (AM) | 12/01/2021 |
Mechanical Rough-in Inspection | Partial Pass | 12/8/2021 (12:30 - 2:30) | 12/8/2021 (PM) | 12/08/2021 |
Mechanical Rough-in Inspection | Partial Pass | 12/21/2021 (12:30 - 2:30) | 12/21/2021 (PM) | 12/21/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/21/2021
2nd floor rough basement ok to cover rooms
|
||||
Mechanical Rough-in Inspection | Partial Pass | 1/5/2022 (12:30 - 2:30) | 1/5/2022 (PM) | 01/05/2022 |
Mechanical Rough-in Inspection | Partial Pass | 1/10/2022 (10:00 - 12:00) | 1/10/2022 (AM) | 01/10/2022 |
Mechanical Rough-in Inspection | Partial Pass | 1/19/2022 (10:00 - 12:00) | 1/19/2022 (AM) | 01/19/2022 |
Mechanical Rough-in Inspection | Partial Pass | 1/21/2022 (12:30 - 2:30) | 1/21/2022 (PM) | 01/21/2022 |
Mechanical Rough-in Inspection | Partial Pass | 1/27/2022 (12:30 - 2:30) | 1/27/2022 (PM) | 01/27/2022 |
Mechanical Rough-in Inspection | Partial Pass | 2/22/2022 (8:00 - 10:00) | 2/22/2022 (AM) | 02/22/2022 |
Mechanical Rough-in Inspection | Partial Pass | 3/11/2022 (8:00 - 10:00) | 3/11/2022 (AM) | 03/11/2022 |
100 psi air test for common areas and resident units. Ongoing work. | ||||
Corrections:
Miscellaneous/Other
Comment Only
03/11/2022
Hydro air test - 100 PSI air test. A. Common areas and resident units.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 3/17/2022 (12:30 - 2:30) | 3/17/2022 (PM) | 03/17/2022 |
Mechanical Rough-in Inspection | Partial Pass | 3/31/2022 (10:00 - 12:00) | 3/31/2022 (AM) | 03/31/2022 |
Mechanical Rough-in Inspection | Partial Pass | 4/14/2022 (10:00 - 12:00) | 4/14/2022 (AM) | 04/14/2022 |
Mechanical Rough-in Inspection | Partial Pass | 4/27/2022 (12:30 - 2:30) | 4/27/2022 (PM) | 04/27/2022 |
Mechanical Final Inspection | Passed | 5/12/2022 (12:30 - 2:30) | 5/12/2022 (PM) | 05/12/2022 |
Mechanical Final Inspection | Passed | 5/13/2022 (12:30 - 2:30) | 5/13/2022 (PM) | 05/13/2022 |