Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Final Inspection | Pending | |||
Mechanical Rough-in Inspection | Passed | 11/18/2019 (8:00 - 10:00) | 11/18/2019 (AM) | 11/18/2019 |
Mechanical Final Inspection | Passed | 12/23/2019 (8:00 - 10:00) | 12/23/2019 (AM) | 12/23/2019 |
Called | ||||
Mechanical Final Inspection | Partial Pass | 2/24/2020 (10:00 - 12:00) | 2/24/2020 (AM) | 02/24/2020 |
12/30/2019: These guys called for an inspection of the gasline but it was finaled already. After talking with Jesse he wants it scheduled. According to Jesse, the job tinners and fitters don't always communicate. So I called Troy about scheduling. Troy is going to call Ambrose to find out who the fitter is cuz he's not sure. They will call back. dheile 12/30/2019 9:03 AM | ||||
Corrections:
Miscellaneous/Other
Comment Only
02/24/2020
Phase 2 mechanical supply's and diffusers installed, balancing is being done at this time for this section of turnover... approved
|