PRMH201913983
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Pending | |||
Mechanical Final Inspection | Pending | |||
Mechanical Rough-in Inspection | Partial Pass | 10/20/2020 (10:00 - 12:00) | 10/20/2020 (AM) | 10/20/2020 |
Mechanical Rough-in Inspection | Partial Pass | 10/23/2020 (8:00 - 10:00) | 10/23/2020 (AM) | 10/23/2020 |
Mechanical Rough-in Inspection | Partial Pass | 10/23/2020 (8:00 - 10:00) | 10/23/2020 (AM) | 10/23/2020 |
Mechanical Rough-in Inspection | Partial Pass | 12/14/2020 (10:00 - 12:00) | 12/14/2020 (AM) | 12/14/2020 |
Mechanical Rough-in Inspection | Partial Pass | 12/18/2020 (10:00 - 12:00) | 12/18/2020 (AM) | 12/18/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/18/2020
2nd floor ri and shafts insulated ok to cover
|
||||
Mechanical Rough-in Inspection | Partial Pass | 1/13/2021 (10:00 - 12:00) | 1/13/2021 (AM) | 01/13/2021 |
Corrections:
Miscellaneous/Other
Comment Only
01/13/2021
West side 5th floor soffits
|
||||
Mechanical Rough-in Inspection | Partial Pass | 1/19/2021 (12:30 - 2:30) | 1/19/2021 (PM) | 01/19/2021 |
Mechanical Rough-in Inspection | Partial Pass | 1/27/2021 (10:00 - 12:00) | 1/27/2021 (AM) | 01/27/2021 |
Corrections:
Miscellaneous/Other
Comment Only
01/27/2021
4th fl soffits and 1st floor RI
|
||||
Mechanical Rough-in Inspection | Partial Pass | 2/2/2021 (12:30 - 2:30) | 2/2/2021 (PM) | 02/02/2021 |
Mechanical Rough-in Inspection | Partial Pass | 2/10/2021 (12:30 - 2:30) | 2/10/2021 (PM) | 02/10/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/10/2021
3rd floor soffits and bath fans
|
||||
Mechanical Rough-in Inspection | Passed | 2/12/2021 (10:00 - 12:00) | 2/12/2021 (AM) | 02/12/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/12/2021
Finished 3rd fl soffits
|
||||
Mechanical Rough-in Inspection | Partial Pass | 2/25/2021 (10:00 - 12:00) | 2/25/2021 (AM) | 02/25/2021 |
2nd floor - east and west - 18 total living units. A. Rough in for soffit duct and bathroom exhaust fans, and kitchen exhaust stub in only. B. Generator pipe shaft with mineral wool sound insulation not ready. C. All Fire-caulking inspection performed by Braun Intertec. Mechanical rough in passed. | ||||
Corrections:
Miscellaneous/Other
Comment Only
02/25/2021
2nd floor - east and west wing. A. Interior soffit duct, and exhaust fans.
B. Generator pipe shaft with 3 inch mineral wool.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 3/11/2021 (10:00 - 12:00) | 3/11/2021 (AM) | 03/11/2021 |
Mechanical Rough-in Inspection | Partial Pass | 3/16/2021 (10:00 - 12:00) | 3/16/2021 (AM) | 03/16/2021 |
Mechanical Rough-in Inspection | Partial Pass | 3/18/2021 (10:00 - 12:00) | 3/18/2021 (AM) | 03/18/2021 |
Mechanical Rough-in Inspection | Partial Pass | 3/25/2021 (10:00 - 12:00) | 3/25/2021 (AM) | 03/25/2021 |
Mechanical Rough-in Inspection | Partial Pass | 5/6/2021 (12:30 - 2:30) | 5/6/2021 (PM) | 05/06/2021 |
Corrections:
Miscellaneous/Other
Comment Only
05/06/2021
2nd floor common atrium area ok to cover
|
||||
Mechanical Final Inspection | Partial Pass | 7/7/2021 (10:00 - 12:00) | 7/7/2021 (AM) | 07/07/2021 |
Mechanical Rough-in Inspection | Partial Pass | 7/12/2021 (10:00 - 12:00) | 7/12/2021 (AM) | 07/12/2021 |
Scott called and cancled this inspection. | ||||
Mechanical Final Inspection | Partial Pass | 7/15/2021 (12:30 - 2:30) | 7/15/2021 (PM) | 07/15/2021 |
Mechanical Final Inspection | Partial Pass | 7/19/2021 (12:30 - 2:30) | 7/19/2021 (PM) | 07/19/2021 |
Mechanical Final Inspection | Partial Pass | 7/20/2021 (12:30 - 2:30) | 7/20/2021 (PM) | 07/20/2021 |
Mechanical Final Inspection | Partial Pass | 9/1/2021 (12:30 - 2:30) | 9/1/2021 (PM) | 09/01/2021 |