PRMH201914142
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Rough-in Inspection | Failed | 11/26/2019 (8:00 - 10:00) | 11/26/2019 (AM) | 11/26/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/26/2019
Materials in plenum not plenum rated need to duct return
|
||||
| Mechanical Final Inspection | Not Ready | 11/26/2019 (8:00 - 10:00) | 11/26/2019 (AM) | 11/26/2019 |
| Mechanical Rough-in Inspection | Passed | 11/27/2019 (10:00 - 12:00) | 11/27/2019 (AM) | 11/27/2019 |
| Mechanical Final Inspection | Passed | 11/27/2019 (10:00 - 12:00) | 11/27/2019 (AM) | 11/27/2019 |