PRMH201915226
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Partial Pass | 7/8/2020 (8:00 - 10:00) | 7/8/2020 (AM) | 07/08/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/08/2020
4th floor partial phase 1
|
||||
Mechanical Rough-in Inspection | Partial Pass | 7/13/2020 (12:30 - 2:30) | 7/13/2020 (PM) | 07/13/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/13/2020
4th floor to fire wall
|
||||
Mechanical Rough-in Inspection | Partial Pass | 7/20/2020 (10:00 - 12:00) | 7/20/2020 (AM) | 07/20/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/20/2020
2nd and 3 floor phase 1 RI ok
|
||||
Mechanical Rough-in Inspection | Partial Pass | 7/22/2020 (2:30 - 3:30) | 7/22/2020 (PM) | 07/22/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/22/2020
4th floor phase 1 soffits
|
||||
Mechanical Rough-in Inspection | Partial Pass | 7/23/2020 (2:30 - 3:30) | 7/23/2020 (PM) | 07/23/2020 |
Mechanical Rough-in Inspection | Partial Pass | 7/27/2020 (12:30 - 2:30) | 7/27/2020 (PM) | 07/27/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/27/2020
4th floor soffits
|
||||
Mechanical Rough-in Inspection | Partial Pass | 8/5/2020 (12:30 - 2:30) | 8/5/2020 (PM) | 08/05/2020 |
Mechanical Rough-in Inspection | Partial Pass | 8/6/2020 (12:30 - 2:30) | 8/6/2020 (PM) | 08/06/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/06/2020
3rd floor soffits and ri on first floor
|
||||
Mechanical Rough-in Inspection | Passed | 8/20/2020 (12:30 - 2:30) | 8/20/2020 (PM) | 08/20/2020 |
Mechanical Rough-in Inspection | Partial Pass | 8/26/2020 (2:30 - 3:30) | 8/26/2020 (PM) | 08/26/2020 |
Mechanical Rough-in Inspection | Partial Pass | 9/8/2020 (12:30 - 2:30) | 9/8/2020 (PM) | 09/08/2020 |
Mechanical Rough-in Inspection | Partial Pass | 9/16/2020 (12:30 - 2:30) | 9/16/2020 (PM) | 09/16/2020 |
Mechanical Rough-in Inspection | Passed | 9/17/2020 (12:30 - 2:30) | 9/17/2020 (PM) | 09/17/2020 |
Mechanical Final Inspection | Partial Pass | 9/24/2020 (12:30 - 2:30) | 9/24/2020 (PM) | 09/24/2020 |
Mechanical Rough-in Inspection | Passed | 9/30/2020 (12:30 - 2:30) | 9/30/2020 (PM) | 09/30/2020 |
Mechanical Rough-in Inspection | Partial Pass | 10/1/2020 (2:30 - 3:30) | 10/1/2020 (PM) | 10/01/2020 |
Mechanical Rough-in Inspection | Passed | 10/8/2020 (12:30 - 2:30) | 10/8/2020 (PM) | 10/08/2020 |
Mechanical Rough-in Inspection | Partial Pass | 11/12/2020 (8:00 - 10:00) | 11/12/2020 (AM) | 11/12/2020 |
Corrections:
Miscellaneous/Other
Comment Only
11/12/2020
Pressure test on top half of grease duct
|
||||
Mechanical Rough-in Inspection | Partial Pass | 11/23/2020 (10:00 - 12:00) | 11/23/2020 (AM) | 11/23/2020 |
Corrections:
Miscellaneous/Other
Comment Only
11/23/2020
Light test on test of grease duct ok to wrap
|
||||
Mechanical Final Inspection | Partial Pass | 12/15/2020 (12:30 - 2:30) | 12/15/2020 (PM) | 12/15/2020 |
Mechanical Final Inspection | Partial Pass | 12/28/2020 (2:30 - 3:30) | 12/28/2020 (PM) | 12/28/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/28/2020
3rd and 2nd floor finals on units
|
||||
Mechanical Final Inspection | Partial Pass | 1/21/2021 (12:30 - 2:30) | 1/21/2021 (PM) | 01/21/2021 |
Mechanical Final Inspection | Partial Pass | 2/11/2021 (12:30 - 2:30) | 2/11/2021 (PM) | 02/11/2021 |
Mechanical Final Inspection | Partial Pass | 2/16/2021 (12:30 - 2:30) | 2/16/2021 (PM) | 02/16/2021 |
Mechanical Final Inspection | Passed | 2/18/2021 (12:30 - 2:30) | 2/18/2021 (PM) | 02/18/2021 |