Permit Application Status

PRMH201915226


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRMH201915226
Mechanical/HVAC
Finaled
UNITED LAND LLC
Alteration/Repair/Replace
Complete mechanical systems in new 118 unit senior living. Cherrywood Pointe
12/26/2019
01/24/2020
08/17/2021
02/18/2021

Locations

Permits

Permit Number: PRMH201915226

Mechanical
Finaled
01/24/2020
08/17/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Rough-in Inspection Partial Pass 7/8/2020 (8:00 - 10:00) 7/8/2020 (AM) 07/08/2020
Corrections:


Miscellaneous/Other
Comment Only
07/08/2020
4th floor partial phase 1

Mechanical Rough-in Inspection Partial Pass 7/13/2020 (12:30 - 2:30) 7/13/2020 (PM) 07/13/2020
Corrections:


Miscellaneous/Other
Comment Only
07/13/2020
4th floor to fire wall

Mechanical Rough-in Inspection Partial Pass 7/20/2020 (10:00 - 12:00) 7/20/2020 (AM) 07/20/2020
Corrections:


Miscellaneous/Other
Comment Only
07/20/2020
2nd and 3 floor phase 1 RI ok

Mechanical Rough-in Inspection Partial Pass 7/22/2020 (2:30 - 3:30) 7/22/2020 (PM) 07/22/2020
Corrections:


Miscellaneous/Other
Comment Only
07/22/2020
4th floor phase 1 soffits

Mechanical Rough-in Inspection Partial Pass 7/23/2020 (2:30 - 3:30) 7/23/2020 (PM) 07/23/2020
Mechanical Rough-in Inspection Partial Pass 7/27/2020 (12:30 - 2:30) 7/27/2020 (PM) 07/27/2020
Corrections:


Miscellaneous/Other
Comment Only
07/27/2020
4th floor soffits

Mechanical Rough-in Inspection Partial Pass 8/5/2020 (12:30 - 2:30) 8/5/2020 (PM) 08/05/2020
Mechanical Rough-in Inspection Partial Pass 8/6/2020 (12:30 - 2:30) 8/6/2020 (PM) 08/06/2020
Corrections:


Miscellaneous/Other
Comment Only
08/06/2020
3rd floor soffits and ri on first floor

Mechanical Rough-in Inspection Passed 8/20/2020 (12:30 - 2:30) 8/20/2020 (PM) 08/20/2020
Mechanical Rough-in Inspection Partial Pass 8/26/2020 (2:30 - 3:30) 8/26/2020 (PM) 08/26/2020
Mechanical Rough-in Inspection Partial Pass 9/8/2020 (12:30 - 2:30) 9/8/2020 (PM) 09/08/2020
Mechanical Rough-in Inspection Partial Pass 9/16/2020 (12:30 - 2:30) 9/16/2020 (PM) 09/16/2020
Mechanical Rough-in Inspection Passed 9/17/2020 (12:30 - 2:30) 9/17/2020 (PM) 09/17/2020
Mechanical Final Inspection Partial Pass 9/24/2020 (12:30 - 2:30) 9/24/2020 (PM) 09/24/2020
Mechanical Rough-in Inspection Passed 9/30/2020 (12:30 - 2:30) 9/30/2020 (PM) 09/30/2020
Mechanical Rough-in Inspection Partial Pass 10/1/2020 (2:30 - 3:30) 10/1/2020 (PM) 10/01/2020
Mechanical Rough-in Inspection Passed 10/8/2020 (12:30 - 2:30) 10/8/2020 (PM) 10/08/2020
Mechanical Rough-in Inspection Partial Pass 11/12/2020 (8:00 - 10:00) 11/12/2020 (AM) 11/12/2020
Corrections:


Miscellaneous/Other
Comment Only
11/12/2020
Pressure test on top half of grease duct

Mechanical Rough-in Inspection Partial Pass 11/23/2020 (10:00 - 12:00) 11/23/2020 (AM) 11/23/2020
Corrections:


Miscellaneous/Other
Comment Only
11/23/2020
Light test on test of grease duct ok to wrap

Mechanical Final Inspection Partial Pass 12/15/2020 (12:30 - 2:30) 12/15/2020 (PM) 12/15/2020
Mechanical Final Inspection Partial Pass 12/28/2020 (2:30 - 3:30) 12/28/2020 (PM) 12/28/2020
Corrections:


Miscellaneous/Other
Comment Only
12/28/2020
3rd and 2nd floor finals on units

Mechanical Final Inspection Partial Pass 1/21/2021 (12:30 - 2:30) 1/21/2021 (PM) 01/21/2021
Mechanical Final Inspection Partial Pass 2/11/2021 (12:30 - 2:30) 2/11/2021 (PM) 02/11/2021
Mechanical Final Inspection Partial Pass 2/16/2021 (12:30 - 2:30) 2/16/2021 (PM) 02/16/2021
Mechanical Final Inspection Passed 2/18/2021 (12:30 - 2:30) 2/18/2021 (PM) 02/18/2021