PRMH202000360
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Final Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
10/23/2024
Refrigerant relief lines through roofs need to extend 7’-3” above roof to mitigate hazard per ANSI guidelines and fix suction side flex connectors on penthouse pumps.
|
||||
Mechanical Rough-in Inspection | Passed | 4/16/2020 (8:00 - 10:00) | 4/16/2020 (AM) | 04/17/2020 |
Corrections:
Miscellaneous/Other
Comment Only
04/17/2020
Air handler room ok to start insulation of duct
|
||||
Mechanical Rough-in Inspection | Passed | 5/26/2020 (10:00 - 12:00) | 5/26/2020 (AM) | 05/26/2020 |
Corrections:
Miscellaneous/Other
Comment Only
05/26/2020
Ok to insulate duct
|
||||
Mechanical Rough-in Inspection | Partial Pass | 6/8/2020 (8:00 - 10:00) | 6/8/2020 (AM) | 06/08/2020 |
Mechanical Final Inspection | Failed | 7/1/2020 (8:00 - 10:00) | 7/1/2020 (AM) | 07/01/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/01/2020
Called multiple times and lef message no answer waited 15 minutes
|
||||
Mechanical Rough-in Inspection | Partial Pass | 7/7/2020 (12:30 - 2:30) | 7/7/2020 (PM) | 07/07/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/07/2020
Gas to generator and boilers all at 25 psi
|
||||
Mechanical Rough-in Inspection | Partial Pass | 7/23/2020 (10:00 - 12:00) | 7/23/2020 (AM) | 07/23/2020 |
Mechanical Rough-in Inspection | Partial Pass | 8/6/2020 (10:00 - 12:00) | 8/6/2020 (AM) | 08/06/2020 |
Mechanical Rough-in Inspection | Partial Pass | 8/17/2020 (8:00 - 10:00) | 8/17/2020 (AM) | 08/17/2020 |
The heating system - Just go to job trailer. | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/17/2020
103# test hydro-verified bled pressure off
|
||||
Mechanical Rough-in Inspection | Passed | 8/19/2020 (8:00 - 10:00) | 8/19/2020 (AM) | 08/19/2020 |
Cooling tower - job trailer for check in. | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/19/2020
Final pressure test done with piping
|
||||
Mechanical Rough-in Inspection | Passed | 8/24/2020 (10:00 - 12:00) | 8/24/2020 (AM) | 08/24/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/24/2020
Need fire damper test and start up paper work on equipment ok to temp co
|
||||
Mechanical Rough-in Inspection | Passed | 8/26/2020 (10:00 - 12:00) | 8/26/2020 (AM) | 08/26/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/26/2020
Fire dampers into corridor ok need to see smokes on unit shut down
|
||||
Mechanical Final Inspection | Partial Pass | 10/21/2024 (12:30 - 2:30) | 10/21/2024 (PM) | 10/23/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
10/23/2024
Refrigerant relief lines through roofs need to extend 7’-3” above roof to mitigate hazard per ANSI guidelines and fix suction side flex connectors on penthouse pumps.
|