Permit Application Status

PRMH202000360


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRMH202000360
Mechanical/HVAC
Permit(s) Issued
SKYWATER TECH FOUNDRY INC
Other
Building Expansion at Skywater
01/13/2020
01/31/2020
04/21/2025

Locations

Permits

Permit Number: PRMH202000360

Mechanical
Permit(s) Issued
01/31/2020
04/21/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Final Inspection Pending
Corrections:


Miscellaneous/Other
Outstanding
10/23/2024
Refrigerant relief lines through roofs need to extend 7’-3” above roof to mitigate hazard per ANSI guidelines and fix suction side flex connectors on penthouse pumps.

Mechanical Rough-in Inspection Passed 4/16/2020 (8:00 - 10:00) 4/16/2020 (AM) 04/17/2020
Corrections:


Miscellaneous/Other
Comment Only
04/17/2020
Air handler room ok to start insulation of duct

Mechanical Rough-in Inspection Passed 5/26/2020 (10:00 - 12:00) 5/26/2020 (AM) 05/26/2020
Corrections:


Miscellaneous/Other
Comment Only
05/26/2020
Ok to insulate duct

Mechanical Rough-in Inspection Partial Pass 6/8/2020 (8:00 - 10:00) 6/8/2020 (AM) 06/08/2020
Mechanical Final Inspection Failed 7/1/2020 (8:00 - 10:00) 7/1/2020 (AM) 07/01/2020
Corrections:


Miscellaneous/Other
Comment Only
07/01/2020
Called multiple times and lef message no answer waited 15 minutes

Mechanical Rough-in Inspection Partial Pass 7/7/2020 (12:30 - 2:30) 7/7/2020 (PM) 07/07/2020
Corrections:


Miscellaneous/Other
Comment Only
07/07/2020
Gas to generator and boilers all at 25 psi

Mechanical Rough-in Inspection Partial Pass 7/23/2020 (10:00 - 12:00) 7/23/2020 (AM) 07/23/2020
Mechanical Rough-in Inspection Partial Pass 8/6/2020 (10:00 - 12:00) 8/6/2020 (AM) 08/06/2020
Mechanical Rough-in Inspection Partial Pass 8/17/2020 (8:00 - 10:00) 8/17/2020 (AM) 08/17/2020
The heating system - Just go to job trailer.
Corrections:


Miscellaneous/Other
Comment Only
08/17/2020
103# test hydro-verified bled pressure off

Mechanical Rough-in Inspection Passed 8/19/2020 (8:00 - 10:00) 8/19/2020 (AM) 08/19/2020
Cooling tower - job trailer for check in.
Corrections:


Miscellaneous/Other
Comment Only
08/19/2020
Final pressure test done with piping

Mechanical Rough-in Inspection Passed 8/24/2020 (10:00 - 12:00) 8/24/2020 (AM) 08/24/2020
Corrections:


Miscellaneous/Other
Comment Only
08/24/2020
Need fire damper test and start up paper work on equipment ok to temp co

Mechanical Rough-in Inspection Passed 8/26/2020 (10:00 - 12:00) 8/26/2020 (AM) 08/26/2020
Corrections:


Miscellaneous/Other
Comment Only
08/26/2020
Fire dampers into corridor ok need to see smokes on unit shut down

Mechanical Final Inspection Partial Pass 10/21/2024 (12:30 - 2:30) 10/21/2024 (PM) 10/23/2024
Corrections:


Miscellaneous/Other
Carried Forward
10/23/2024
Refrigerant relief lines through roofs need to extend 7’-3” above roof to mitigate hazard per ANSI guidelines and fix suction side flex connectors on penthouse pumps.