Permit Application Status

PRMH202014354


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRMH202014354
Mechanical/HVAC
Finaled
J & B HOLDINGS LLC
Alteration/Repair/Replace
replace 7.5 ton RTU, Add 6 ton RTU, Distribute ductwork per plan, Set and install new make up air and exhaust fans and hoods for kitchen, Install walk in cooler and freezer and refrigeration. Gas work for repiping entire store.
11/17/2020
12/10/2020
02/12/2022
08/16/2021

Locations

Permits

Permit Number: PRMH202014354

Mechanical
Finaled
12/10/2020
02/12/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Rough-in Inspection Partial Pass 12/17/2020 (10:00 - 12:00) 12/17/2020 (AM) 12/17/2020
Mechanical Rough-in Inspection Passed 12/30/2020 (8:00 - 10:00) 12/30/2020 (AM) 12/30/2020
Mechanical Rough-in Inspection Partial Pass 4/20/2021 (10:00 - 12:00) 4/20/2021 (AM) 04/20/2021
Mechanical Rough-in Inspection Passed 6/21/2021 (10:00 - 12:00) 6/21/2021 (AM) 06/21/2021
Corrections:


Miscellaneous/Other
Comment Only
06/21/2021
Ok to pad out dining area

Mechanical Final Inspection Failed 8/11/2021 (10:00 - 12:00) 8/11/2021 (AM) 08/11/2021
7/27/21 Contractor called to cancel 7/28/21 final as fire suppression is delayed. jms
Mechanical Final Inspection Passed 8/16/2021 (8:00 - 10:00) 8/16/2021 (AM) 08/16/2021