PRMH202100970
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Pending | |||
Mechanical Rough-in Inspection | Partial Pass | 4/22/2021 (8:00 - 10:00) | 4/22/2021 (AM) | 04/22/2021 |
Mechanical Rough-in Inspection | Partial Pass | 6/24/2021 (10:00 - 12:00) | 05/07/2021 | |
Corrections:
Miscellaneous/Other
Comment Only
05/07/2021
Viewed bathroom exhaust piping to bath fans at floors 1-4, piping is sealed.
Connection through roof and insulation was not done yet, an to be inspected when ready.
|
||||
Mechanical Final Inspection | Partial Pass | 5/10/2021 (12:30 - 2:30) | 5/10/2021 (PM) | 05/10/2021 |
Corrections:
Miscellaneous/Other
Comment Only
05/10/2021
Bathroom venting in ceilings to be covered floors 1,2&3, has been inspected and approved.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 6/24/2021 (10:00 - 12:00) | 6/24/2021 (AM) | 06/24/2021 |
Corrections:
Miscellaneous/Other
Comment Only
06/24/2021
Gas line air test holding pressure and approved.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 6/28/2021 (8:00 - 10:00) | 6/28/2021 (AM) | 06/28/2021 |
Mechanical Final Inspection | Partial Pass | 7/19/2021 (10:00 - 12:00) | 7/19/2021 (AM) | 07/19/2021 |
Mechanical Final Inspection | Failed | 8/10/2021 (10:00 - 12:00) | 8/10/2021 (AM) | 08/10/2021 |
Mechanical Final Inspection | Failed | 8/11/2021 (8:00 - 10:00) | 8/11/2021 (AM) | 08/11/2021 |
Mechanical Final Inspection | Passed | 8/19/2021 (8:00 - 10:00) | 8/19/2021 (AM) | 08/24/2021 |