PRMH202101789
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Pending | |||
Mechanical Rough-in Inspection | Partial Pass | 3/5/2021 (10:00 - 12:00) | 3/5/2021 (AM) | 03/05/2021 |
Work is not completed at this time. Reschedule with Jesse Soller next week. Contact is Chris. | ||||
Corrections:
Miscellaneous/Other
Outstanding
03/05/2021
Mechanical rough in. - not ready. Still working on ductwork.
A. Please reschedule with city of Bloomington commercial mechanical inspector Jesse Soller, next week. ( City inspection line - 952-563-8930 )
|
||||
Mechanical Final Inspection | Partial Pass | 3/12/2021 (12:30 - 2:30) | 3/12/2021 (PM) | 03/12/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/12/2021
Almost all hard pipe installed need to see flex to diffusers and egg crate in
|
||||
Mechanical Final Inspection | Passed | 4/19/2021 (10:00 - 12:00) | 4/19/2021 (AM) | 04/19/2021 |