PRMH202108036
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Rough-in Inspection | Partial Pass | 7/27/2021 (12:30 - 2:30) | 7/27/2021 (PM) | 07/27/2021 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/27/2021
Ok to sheet rock lower walls need to see flex duct and second floor duct in walls
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 8/4/2021 (12:30 - 2:30) | 8/4/2021 (PM) | 08/04/2021 |
| Progress on roof top insulated ductwork for new individual HVAC units, for NEW cadaver lab. Main floor and 2nd floor, new vertical shaft ductwork, thru 2nd floor, having firecaulk at 2nd level floor of building, having rated shaft, for main level Cadaver lab. Passed. ( Ongoing inspections.) | ||||
| Mechanical Rough-in Inspection | Passed | 8/24/2021 (2:30 - 3:30) | 8/24/2021 (PM) | 08/24/2021 |
| Mechanical Final Inspection | Partial Pass | 9/7/2021 (12:30 - 2:30) | 9/7/2021 (PM) | 09/07/2021 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/07/2021
Final - HVAC. A. Jessie mechanical inspector is out of office for 2 days.
B. Balance report for HVAC and final fire marshal alarm and final on new mechanical roof top dedicated system still pending.
C. Final plumbing required, and contractor still need to install eye washing stations for new remodeled classrooms on the main level west end.
D. All trade finals, must be final approved, (plumbing, mechanical, electrical, and fire marshal final) prior to building final.
|
||||
| Mechanical Final Inspection | Passed | 09/29/2021 | ||