Summary

PRMH202109161
Mechanical/HVAC
Expired
BLMGTN SCHOOL DIST #271
Alteration/Repair/Replace
Mechanical plant for Jefferson-Olson school campus.
07/16/2021
09/02/2021
02/26/2023

Locations

Permits

Permit Number: PRMH202109161

Mechanical
Expired
09/02/2021
02/26/2023

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Final Inspection Pending
Mechanical Rough-in Inspection Pending
Corrections:


Miscellaneous/Other
Outstanding
08/30/2022
Visual on sealed ductwork prior to duct insulation, for new interior main plant building, suppling Jefferson and Olson schools. A. Label and provide access to all mechanical dampers.

Mechanical Rough-in Inspection Partial Pass 11/16/2021 (2:30 - 3:30) 11/16/2021 (PM) 11/16/2021
Mechanical Rough-in Inspection Partial Pass 12/16/2021 (12:30 - 2:30) 12/16/2021 (PM) 12/16/2021
Corrections:


Miscellaneous/Other
Comment Only
12/16/2021
Pressure test piping stubbed into jefferson high school Mech room

Mechanical Rough-in Inspection Partial Pass 4/6/2022 (12:30 - 2:30) 4/6/2022 (PM) 04/06/2022
Mechanical Rough-in Inspection Partial Pass 4/12/2022 (12:30 - 2:30) 4/12/2022 (PM) 04/12/2022
Mechanical Rough-in Inspection Partial Pass 4/19/2022 (12:30 - 2:30) 4/19/2022 (PM) 04/19/2022
Mechanical Rough-in Inspection Passed 4/26/2022 (12:30 - 2:30) 4/26/2022 (PM) 04/26/2022
Mechanical Rough-in Inspection Partial Pass 5/3/2022 (12:30 - 2:30) 5/3/2022 (PM) 05/03/2022
Mechanical Rough-in Inspection Partial Pass 7/15/2022 (8:00 - 10:00) 7/15/2022 (AM) 07/15/2022
Corrections:


Miscellaneous/Other
Carried Forward
07/15/2022
Visual on sealed ductwork prior to duct insulation, for new interior main plant building, suppling Jefferson and Olson schools. A. Label and provide access to all mechanical dampers.

Mechanical Rough-in Inspection Partial Pass 7/28/2022 (12:30 - 2:30) 7/28/2022 (PM) 07/28/2022
Corrections:


Miscellaneous/Other
Carried Forward
07/28/2022
Visual on sealed ductwork prior to duct insulation, for new interior main plant building, suppling Jefferson and Olson schools. A. Label and provide access to all mechanical dampers.

Mechanical Rough-in Inspection Partial Pass 8/30/2022 (12:30 - 2:30) 8/30/2022 (PM) 08/30/2022
Corrections:


Miscellaneous/Other
Carried Forward
08/30/2022
Visual on sealed ductwork prior to duct insulation, for new interior main plant building, suppling Jefferson and Olson schools. A. Label and provide access to all mechanical dampers.