PRMH202113483
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Partial Pass | 12/14/2021 (10:00 - 12:00) | 12/14/2021 (AM) | 12/14/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/14/2021
Phase 1 ducting up to office area… approved
|
||||
Mechanical Rough-in Inspection | Partial Pass | 1/11/2022 (8:00 - 10:00) | 1/11/2022 (AM) | 01/11/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/11/2022
Ducting in the offices area… approved.
30 # air test on the gas piping in kitchen inside furred kitchen wall… approved. (Line was pressured from shutoff to end run of piping).
|
||||
Mechanical Rough-in Inspection | Failed | 6/28/2022 (10:00 - 12:00) | 6/28/2022 (AM) | 06/28/2022 |
Corrections:
Miscellaneous/Other
Comment Only
06/28/2022
Need to insulate duct in second phase
|
||||
Mechanical Rough-in Inspection | Partial Pass | 7/12/2022 (10:00 - 12:00) | 7/12/2022 (AM) | 07/12/2022 |
Mechanical Final Inspection | Failed | 8/24/2022 (10:00 - 12:00) | 8/24/2022 (AM) | 08/24/2022 |
Mechanical Final Inspection | Failed | 10/31/2022 (10:00 - 12:00) | 10/31/2022 (AM) | 10/31/2022 |
Corrections:
Miscellaneous/Other
Comment Only
10/31/2022
Need to have a supervised start up on make up air unit
|
||||
Mechanical Final Inspection | Passed | 11/07/2022 |