Summary

PRMH202202950
Mechanical/HVAC
Finaled
CITY OF BLOOMINGTON
Other
Hydronic and gas piping for new fire station
03/24/2022
06/09/2022
11/14/2023
05/18/2023

Locations

Permits

Permit Number: PRMH202202950

Mechanical
Finaled
06/09/2022
11/14/2023

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Rough-in Inspection Partial Pass 11/2/2022 (2:30 - 3:30) 11/2/2022 (PM) 11/02/2022
Corrections:


Miscellaneous/Other
Comment Only
11/02/2022
In floor on second pressure test ok to pour over

Mechanical Rough-in Inspection Partial Pass 12/19/2022 (12:30 - 2:30) 12/19/2022 (PM) 12/19/2022
Mechanical Rough-in Inspection Partial Pass 1/10/2023 (12:30 - 2:30) 1/10/2023 (PM) 01/10/2023
Mechanical Rough-in Inspection Partial Pass 2/8/2023 (12:30 - 2:30) 2/8/2023 (PM) 02/08/2023
Mechanical Rough-in Inspection Partial Pass 3/1/2023 (10:00 - 12:00) 3/1/2023 (AM) 03/01/2023
Mechanical Final Inspection Passed 5/17/2023 (10:00 - 12:00) 5/17/2023 (AM) 05/18/2023
Corrections:


Miscellaneous/Other
Comment Only
05/18/2023
Gas and hydronic should are good boilers are based