Summary

PRMH202210119
Mechanical/HVAC
Finaled
NOBLE APARTMENTS LLC
Other
Complete hvac system in new 149 unit multifamily building
08/11/2022
09/06/2022
07/27/2024
01/29/2024

Locations

Permits

Permit Number: PRMH202210119

Mechanical
Finaled
09/06/2022
07/27/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Rough-in Inspection Not Ready 5/23/2023 (10:00 - 12:00) 5/23/2023 (AM) 05/23/2023
Mechanical Rough-in Inspection Not Ready 6/15/2023 (8:00 - 10:00) 6/15/2023 (AM) 06/15/2023
Mechanical Rough-in Inspection Partial Pass 6/21/2023 (12:30 - 2:30) 6/21/2023 (PM) 06/21/2023
Corrections:


Miscellaneous/Other
Comment Only
06/21/2023
Visual inspection of a portion of units on 4th floor okay.

Mechanical Rough-in Inspection Partial Pass 6/22/2023 (8:00 - 10:00) 6/22/2023 (AM) 06/22/2023
Corrections:


Miscellaneous/Other
Comment Only
06/22/2023
Visual inspection of a portion of units on 4th floor okay.

Mechanical Rough-in Inspection Partial Pass 6/26/2023 (12:30 - 2:30) 6/26/2023 (PM) 06/26/2023
Corrections:


Miscellaneous/Other
Comment Only
06/26/2023
Visual inspection for remaining units on 4th floor for mechanical okay. Visual inspection for gas, condensate, and line sets on 4th floor also okay.

Mechanical Rough-in Inspection Partial Pass 7/13/2023 (12:30 - 2:30) 7/13/2023 (PM) 07/13/2023
Corrections:


Miscellaneous/Other
Comment Only
07/13/2023
Visual inspection of a portion of rough in’s on 3rd floor okay.

Mechanical Rough-in Inspection Partial Pass 7/17/2023 (12:30 - 2:30) 7/17/2023 (PM) 07/17/2023
Corrections:


Miscellaneous/Other
Comment Only
07/17/2023
Visual inspection okay for a portion units on 3rd floor.

Mechanical Rough-in Inspection Partial Pass 7/18/2023 (12:30 - 2:30) 7/18/2023 (PM) 07/18/2023
Corrections:


Miscellaneous/Other
Comment Only
07/18/2023
Visual inspection of remainder of units on 3rd floor for rough in okay.

Mechanical Rough-in Inspection Partial Pass 7/20/2023 (8:00 - 10:00) 7/20/2023 (AM) 07/20/2023
Corrections:


Miscellaneous/Other
Comment Only
07/20/2023
4th floor: Mechanical: A. Start of living units: A. interior sealed mech supply duct work, for each separate new living units, fire protected by 5/8 inch fire taped gypsum.

Mechanical Rough-in Inspection Partial Pass 7/24/2023 (8:00 - 10:00) 7/24/2023 (AM) 07/24/2023
Corrections:


Miscellaneous/Other
Comment Only
07/24/2023
Visual inspection of soffit ducting on a portion of units on 4th floor okay.

Mechanical Rough-in Inspection Partial Pass 7/25/2023 (7:00 - 8:00) 7/25/2023 (AM) 07/25/2023
Corrections:


Miscellaneous/Other
Comment Only
07/25/2023
Visual inspection of soffit ducting for remaining units on 4th floor okay.

Mechanical Rough-in Inspection Partial Pass 8/3/2023 (12:30 - 2:30) 8/3/2023 (PM) 08/03/2023
Mechanical Rough-in Inspection Partial Pass 8/7/2023 (8:00 - 10:00) 8/7/2023 (AM) 08/07/2023
Mechanical Rough-in Inspection Partial Pass 8/8/2023 (8:00 - 10:00) 8/8/2023 (AM) 08/08/2023
Mechanical Rough-in Inspection Partial Pass 8/9/2023 (8:00 - 10:00) 8/9/2023 (AM) 08/09/2023
Mechanical Rough-in Inspection Partial Pass 8/10/2023 (8:00 - 10:00) 8/10/2023 (AM) 08/10/2023
Mechanical Rough-in Inspection Partial Pass 8/17/2023 (10:00 - 12:00) 8/17/2023 (AM) 08/17/2023
Mechanical Rough-in Inspection Partial Pass 8/28/2023 (8:00 - 10:00) 8/28/2023 (AM) 08/28/2023
Mechanical Rough-in Inspection Partial Pass 8/30/2023 (12:30 - 2:30) 8/30/2023 (PM) 08/30/2023
Mechanical Rough-in Inspection Partial Pass 8/31/2023 (12:30 - 2:30) 8/31/2023 (PM) 08/31/2023
Mechanical Rough-in Inspection Partial Pass 9/5/2023 (12:30 - 2:30) 9/5/2023 (PM) 09/05/2023
Mechanical Rough-in Inspection Partial Pass 9/21/2023 (10:00 - 12:00) 9/21/2023 (AM) 09/21/2023
Mechanical Rough-in Inspection Partial Pass 9/26/2023 (12:30 - 2:30) 9/26/2023 (PM) 09/26/2023
Cancelled by contractor today. [jsmidt @ 09/26/2023 8:24 AM]
Mechanical Rough-in Inspection Partial Pass 9/27/2023 (12:30 - 2:30) 9/27/2023 (PM) 09/27/2023
Mechanical Rough-in Inspection Partial Pass 10/4/2023 (10:00 - 12:00) 10/4/2023 (AM) 10/04/2023
Mechanical Rough-in Inspection Passed 10/9/2023 (12:30 - 2:30) 10/9/2023 (PM) 10/09/2023
Mechanical Rough-in Inspection Partial Pass 10/11/2023 (10:00 - 12:00) 10/11/2023 (AM) 10/11/2023
Mechanical Rough-in Inspection Passed 10/24/2023 (8:00 - 10:00) 10/24/2023 (AM) 10/24/2023
Mechanical Rough-in Inspection Partial Pass 11/1/2023 (12:30 - 2:30) 11/1/2023 (PM) 11/01/2023
Mechanical Rough-in Inspection Passed 11/15/2023 (8:00 - 10:00) 11/15/2023 (AM) 11/15/2023
Mechanical Rough-in Inspection Partial Pass 11/16/2023 (8:00 - 10:00) 11/16/2023 (AM) 11/16/2023
Mechanical Rough-in Inspection Partial Pass 12/21/2023 (12:30 - 2:30) 12/21/2023 (PM) 12/21/2023
Mechanical Final Inspection Partial Pass 1/9/2024 (8:00 - 10:00) 1/9/2024 (AM) 01/09/2024
Mechanical Final Inspection Passed 1/10/2024 (8:00 - 10:00) 1/10/2024 (AM) 01/10/2024
Mechanical Final Inspection Partial Pass 1/11/2024 (8:00 - 10:00) 1/11/2024 (AM) 01/11/2024
Mechanical Final Inspection Partial Pass 1/16/2024 (8:00 - 10:00) 1/16/2024 (AM) 01/16/2024
Mechanical Final Inspection Partial Pass 1/17/2024 (8:00 - 10:00) 1/17/2024 (AM) 01/17/2024
Mechanical Final Inspection Partial Pass 1/18/2024 (8:00 - 10:00) 1/18/2024 (AM) 01/18/2024
Mechanical Final Inspection Partial Pass 1/22/2024 (2:30 - 3:30) 1/22/2024 (PM) 01/23/2024
Mechanical Final Inspection Passed 1/29/2024 (8:00 - 10:00) 1/29/2024 (AM) 01/29/2024