PRMH202213743
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Partial Pass | 2/6/2023 (8:00 - 10:00) | 2/6/2023 (AM) | 02/06/2023 |
Corrections:
Miscellaneous/Other
Comment Only
02/06/2023
Temp gas ok and pre inspection walk through
|
||||
Mechanical Rough-in Inspection | Partial Pass | 3/14/2023 (8:00 - 10:00) | 3/14/2023 (AM) | 03/17/2023 |
Mechanical Rough-in Inspection | Partial Pass | 3/27/2023 (8:00 - 10:00) | 3/27/2023 (AM) | 03/27/2023 |
Mechanical Rough-in Inspection | Passed | 3/30/2023 (10:00 - 12:00) | 3/30/2023 (AM) | 03/30/2023 |
Mechanical Rough-in Inspection | Partial Pass | 4/4/2023 (8:00 - 10:00) | 4/4/2023 (AM) | 04/04/2023 |
Mechanical Rough-in Inspection | Partial Pass | 4/6/2023 (8:00 - 10:00) | 4/6/2023 (AM) | 04/06/2023 |
Mechanical Rough-in Inspection | Partial Pass | 4/10/2023 (8:00 - 10:00) | 4/10/2023 (AM) | 04/10/2023 |
Mechanical Rough-in Inspection | Partial Pass | 4/11/2023 (12:30 - 2:30) | 4/11/2023 (PM) | 04/11/2023 |
Mechanical Rough-in Inspection | Partial Pass | 4/13/2023 (10:00 - 12:00) | 4/13/2023 (AM) | 04/13/2023 |
Mechanical Rough-in Inspection | Partial Pass | 4/24/2023 (8:00 - 10:00) | 4/24/2023 (AM) | 04/24/2023 |
Mechanical Rough-in Inspection | Passed | 4/25/2023 (8:00 - 10:00) | 4/25/2023 (AM) | 04/25/2023 |
Mechanical Rough-in Inspection | Partial Pass | 4/26/2023 (10:00 - 12:00) | 4/26/2023 (AM) | 04/26/2023 |
Mechanical Rough-in Inspection | Partial Pass | 5/16/2023 (2:30 - 3:30) | 5/16/2023 (PM) | 05/16/2023 |
Mechanical Rough-in Inspection | Passed | 5/19/2023 (10:00 - 12:00) | 5/19/2023 (AM) | 05/19/2023 |
Corrections:
Miscellaneous/Other
Comment Only
05/19/2023
Magic pac gas lines at all units of 2nd floor... approved
Air test on 5 line sets for the condensors in gaage holding at 350 psi... approved
|
||||
Mechanical Rough-in Inspection | Partial Pass | 6/1/2023 (10:00 - 12:00) | 6/1/2023 (AM) | 06/01/2023 |
Corrections:
Miscellaneous/Other
Comment Only
06/01/2023
Piping runs and fire stops on 1st floor areas 2,3,& 4.
Piping and air test to areas 2,3,&4 and SE meter , holding at 31 psi.
Piping and air test to oxendal and NE meter holding at 31 psi.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 06/08/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/08/2023
Duct sealing and rough in on first floor common areas within soffits and partial exposed... approved
|
||||
Progress Inspection | Partial Pass | 06/21/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/21/2023
Phase 2, 6th floor gas piping, nail plates and fire stops through floor and framing plates.... approved
|
||||
Mechanical Rough-in Inspection | Passed | 6/26/2023 (10:00 - 12:00) | 6/26/2023 (AM) | 06/26/2023 |
Corrections:
Miscellaneous/Other
Comment Only
06/26/2023
Phase 2, 5h floor gaslines Rough in and firestops.
6h floor dryer venting in units, and bath fan venting.
Approved
|
||||
Progress Inspection | Partial Pass | 06/30/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/30/2023
Phase two, 4th floorarea 5 and 1/2 of 6... gas piping runs to magic pacs viewed, nail plates and fire stops... approved
|
||||
Progress Inspection | Partial Pass | 07/10/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/10/2023
Gas piping RI for magic pacs in unit of 3rd floor areas 5,6&7... fire stops, piping , and nail plates approved
|
||||
Progress Inspection | Partial Pass | 07/13/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/13/2023
Dryer and bath fan venting of phase 2, floors 4th and 5th. Approved
|
||||
Progress Inspection | Partial Pass | 07/14/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/14/2023
Gas piping , air test at 30psi, nail plates and fire stops on phase 2, level 2... approved
Venting for bath fans, magic pac, and dryer in phase 2, floors 2&3... approved.
|
||||
Progress Inspection | Partial Pass | 07/19/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/19/2023
1st floor phase 2 gas lines and air test (25psi) to piping at meter banks... approved
|
||||
Progress Inspection | Partial Pass | 07/25/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/25/2023
Phase 2 supply ducing in mechanical shafts at level 6, insulation approved. Level 5 ducting install, supports and sealing... approved
|
||||
Progress Inspection | Partial Pass | 08/22/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
08/22/2023
Mechanical shaft ducting in phase 2, areas 5&7 from floors 3-6... approved.
|
||||
Progress Inspection | Partial Pass | 08/25/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
08/25/2023
Mechanicla shaft supply ducts at phase 2, areas 5&7 of second floor added section... approved.
Note... Need to see the ducts capped from first floor prior to cloing shaft.
|
||||
Progress Inspection | Partial Pass | 09/05/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
09/05/2023
Ducting in mechanical shaft of area1, floors 2-6 and terminating at first floor.... approved
|
||||
Mechanical Final Inspection | Partial Pass | 9/12/2023 (8:00 - 10:00) | 9/12/2023 (AM) | 09/12/2023 |
Mechanical Final Inspection | Partial Pass | 9/14/2023 (10:00 - 12:00) | 9/14/2023 (AM) | 09/14/2023 |
Mechanical Final Inspection | Partial Pass | 9/15/2023 (8:00 - 10:00) | 9/15/2023 (AM) | 09/15/2023 |
Mechanical Final Inspection | Partial Pass | 9/18/2023 (10:00 - 12:00) | 9/18/2023 (AM) | 09/20/2023 |
Mechanical Final Inspection | Partial Pass | 9/19/2023 (10:00 - 12:00) | 9/19/2023 (AM) | 09/20/2023 |
Mechanical Final Inspection | Partial Pass | 9/27/2023 (10:00 - 12:00) | 9/27/2023 (AM) | 09/27/2023 |
Mechanical Final Inspection | Partial Pass | 9/28/2023 (10:00 - 12:00) | 9/28/2023 (AM) | 09/28/2023 |
Mechanical Final Inspection | Partial Pass | 9/29/2023 (10:00 - 12:00) | 9/29/2023 (AM) | 09/29/2023 |
Progress Inspection | Passed | 10/5/2023 (12:30 - 2:30) | 10/5/2023 (PM) | 10/05/2023 |
Corrections:
Miscellaneous/Other
Comment Only
10/05/2023
Floor 1 to 6 of phase 2... Ducting at trash shaft with radiation damper installed to bottom of ducting into 1st floor... approved
Remaining transition ducting located on first floor to tie into ducting already inspected... approved
|
||||
Mechanical Final Inspection | Partial Pass | 10/10/2023 (2:30 - 3:30) | 10/10/2023 (PM) | 10/10/2023 |
Mechanical Final Inspection | Partial Pass | 11/1/2023 (10:00 - 12:00) | 11/1/2023 (AM) | 11/01/2023 |
Mechanical Final Inspection | Partial Pass | 11/2/2023 (Morning) | 11/2/2023 (AM) | 11/02/2023 |
Mechanical Final Inspection | Partial Pass | 12/4/2023 (10:00 - 12:00) | 12/4/2023 (AM) | 12/04/2023 |
Mechanical Final Inspection | Partial Pass | 12/5/2023 (8:00 - 10:00) | 12/5/2023 (AM) | 12/05/2023 |
Mechanical Final Inspection | Passed | 12/14/2023 (10:00 - 12:00) | 12/14/2023 (AM) | 12/18/2023 |