Permit Application Status

PRMH202301012


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRMH202301012
Mechanical/HVAC
Finaled
MSP SOUTHPOINT EQUITIES LLC
Alteration/Repair/Replace
New ductwork runouts as needed. Utilize existing VAVs. Add (1) new heat pump for server room.
02/02/2023
02/08/2023
08/21/2023
02/22/2023

Locations

Permits

Permit Number: PRMH202301012

Mechanical
Finaled
02/08/2023
08/21/2023

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Rough-in Inspection Passed 2/22/2023 (12:30 - 2:30) 2/22/2023 (PM) 02/22/2023
Mechanical Final Inspection Passed 2/22/2023 (12:30 - 2:30) 2/22/2023 (PM) 02/22/2023