PRMH202304484
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Final Inspection | Pending | |||
Mechanical Rough-in Inspection | Partial Pass | 7/11/2023 (12:30 - 2:30) | 7/11/2023 (PM) | 07/11/2023 |
Miscellaneous/Other
Comment Only
07/11/2023
Visual inspection and air tests okay for underground hydronic piping on west side of building.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 7/18/2023 (8:00 - 10:00) | 7/18/2023 (AM) | 07/18/2023 |
Miscellaneous/Other
Comment Only
07/18/2023
Visual inspection and air test okay for underground hydronic piping on east side of building.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 8/24/2023 (12:30 - 2:30) | 8/24/2023 (PM) | 08/24/2023 |
Miscellaneous/Other
Comment Only
08/24/2023
Pressure test for snowmelt ok to cover
|
||||
Mechanical Rough-in Inspection | Partial Pass | 10/2/2023 (12:30 - 2:30) | 10/2/2023 (PM) | 10/02/2023 |
Mechanical Rough-in Inspection | Partial Pass | 10/4/2023 (12:30 - 2:30) | 10/4/2023 (PM) | 10/09/2023 |
Mechanical Rough-in Inspection | Partial Pass | 11/2/2023 (2:30 - 3:30) | 11/2/2023 (PM) | 11/02/2023 |
Mechanical Rough-in Inspection | Partial Pass | 11/02/2023 | ||
Mechanical Rough-in Inspection | Partial Pass | 11/7/2023 (12:30 - 2:30) | 11/7/2023 (PM) | 11/07/2023 |
Mechanical Rough-in Inspection | Partial Pass | 11/8/2023 (12:30 - 2:30) | 11/8/2023 (PM) | 11/08/2023 |
Mechanical Rough-in Inspection | Partial Pass | 12/11/2023 (12:30 - 2:30) | 12/11/2023 (PM) | 12/12/2023 |
Mechanical Rough-in Inspection | Partial Pass | 1/16/2024 (10:00 - 12:00) | 1/16/2024 (AM) | 01/16/2024 |
Mechanical Rough-in Inspection | Partial Pass | 3/1/2024 (10:00 - 12:00) | 3/1/2024 (AM) | 03/04/2024 |
Miscellaneous/Other
Comment Only
03/04/2024
Visual inspection of added 3” line okay. Visual inspection of heat pump piping to units okay pending Jesse’s final approval.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 3/7/2024 (8:00 - 10:00) | 3/7/2024 (AM) | 03/07/2024 |
Mechanical Rough-in Inspection | Partial Pass | 3/20/2024 (12:30 - 2:30) | 3/20/2024 (PM) | 03/20/2024 |
Mechanical Rough-in Inspection | Passed | 4/16/2024 (8:00 - 10:00) | 4/16/2024 (AM) | 04/16/2024 |
Miscellaneous/Other
Comment Only
04/16/2024
Fin tube radiant heaters in stair and showroom, and air tests (4 seperate tests) all holding at 100 psi.... approved
|