PRMH202304484
Mechanical/HVAC
Permit(s) Issued
WALSER REAL ESTATE IV LLC
Other
Provide hydronic and gas piping for project. We include: Core Water Piping of (54) Heat Pumps, (1) Ceiling Hung Cabinet Unit Heater, (1) Wall Hung Cabinet Unit Heater, 218' Base Board Commercial Grade, (1) Snowmelt Zone, (3) Radiant Heat Zones, (4) In Floor Heat Pumps, (2) Primary Hot Water Pumps, (6) High Efficiency Condensing Boilers, (1) 150 ton cooling tower, (2) Core Water Pumps w/ VFD's, (2) core Water Pumps w/ no VFD's, (1) 1500 gallon Holding Tank, and piping for (1) AHU. We also include gas piping of: (6) Boilers, (5) Roof Top Units, (3) Make Up Air Units, (2) Water Heaters, (2) Infrared Heaters, (1) Air Handler, (1) Gas Meter, and (2) Gas Unit Heaters.
05/03/2023
05/18/2023
10/13/2024

Locations

Permits

Permit Number: PRMH202304484

Mechanical
Issued

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Final Inspection Pending
Mechanical Rough-in Inspection Partial Pass 7/11/2023 (12:30 - 2:30) 7/11/2023 (PM) 07/11/2023
Miscellaneous/Other
Comment Only
07/11/2023
Visual inspection and air tests okay for underground hydronic piping on west side of building.

Mechanical Rough-in Inspection Partial Pass 7/18/2023 (8:00 - 10:00) 7/18/2023 (AM) 07/18/2023
Miscellaneous/Other
Comment Only
07/18/2023
Visual inspection and air test okay for underground hydronic piping on east side of building.

Mechanical Rough-in Inspection Partial Pass 8/24/2023 (12:30 - 2:30) 8/24/2023 (PM) 08/24/2023
Miscellaneous/Other
Comment Only
08/24/2023
Pressure test for snowmelt ok to cover

Mechanical Rough-in Inspection Partial Pass 10/2/2023 (12:30 - 2:30) 10/2/2023 (PM) 10/02/2023
Mechanical Rough-in Inspection Partial Pass 10/4/2023 (12:30 - 2:30) 10/4/2023 (PM) 10/09/2023
Mechanical Rough-in Inspection Partial Pass 11/2/2023 (2:30 - 3:30) 11/2/2023 (PM) 11/02/2023
Mechanical Rough-in Inspection Partial Pass 11/02/2023
Mechanical Rough-in Inspection Partial Pass 11/7/2023 (12:30 - 2:30) 11/7/2023 (PM) 11/07/2023
Mechanical Rough-in Inspection Partial Pass 11/8/2023 (12:30 - 2:30) 11/8/2023 (PM) 11/08/2023
Mechanical Rough-in Inspection Partial Pass 12/11/2023 (12:30 - 2:30) 12/11/2023 (PM) 12/12/2023
Mechanical Rough-in Inspection Partial Pass 1/16/2024 (10:00 - 12:00) 1/16/2024 (AM) 01/16/2024
Mechanical Rough-in Inspection Partial Pass 3/1/2024 (10:00 - 12:00) 3/1/2024 (AM) 03/04/2024
Miscellaneous/Other
Comment Only
03/04/2024
Visual inspection of added 3” line okay. Visual inspection of heat pump piping to units okay pending Jesse’s final approval.

Mechanical Rough-in Inspection Partial Pass 3/7/2024 (8:00 - 10:00) 3/7/2024 (AM) 03/07/2024
Mechanical Rough-in Inspection Partial Pass 3/20/2024 (12:30 - 2:30) 3/20/2024 (PM) 03/20/2024
Mechanical Rough-in Inspection Passed 4/16/2024 (8:00 - 10:00) 4/16/2024 (AM) 04/16/2024
Miscellaneous/Other
Comment Only
04/16/2024
Fin tube radiant heaters in stair and showroom, and air tests (4 seperate tests) all holding at 100 psi.... approved