PRMH202400395
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Final Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
08/02/2024
Balance reports needed for 2nd and 3rd floor areas.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 2/20/2024 (8:00 - 10:00) | 2/20/2024 (AM) | 02/20/2024 |
Corrections:
Miscellaneous/Other
Comment Only
02/20/2024
Ok to insulate duct on 2nd floor
|
||||
Mechanical Rough-in Inspection | Partial Pass | 2/27/2024 (12:30 - 2:30) | 2/27/2024 (PM) | 02/27/2024 |
Corrections:
Miscellaneous/Other
Comment Only
02/27/2024
Piping and shutoff valves to 7 installed VAV's on 2nd and 3rd floor, pressure test was holding at 80psi.
Insulation of piping is in process.
|
||||
Mechanical Final Inspection | Partial Pass | 3/1/2024 (12:30 - 2:30) | 3/1/2024 (PM) | 03/01/2024 |
Corrections:
Miscellaneous/Other
Comment Only
03/01/2024
2nd floor... all piping insulated and diffusers installed. Final for this floor approved, pending balance report.
|
||||
Miscellaneous/Other
Carried Forward
03/01/2024
Balance report needed for 2nd floor of this remodel.
|
||||
Mechanical Rough-in Inspection | Passed | 4/19/2024 (8:00 - 10:00) | 4/19/2024 (AM) | 04/19/2024 |
Corrections:
Miscellaneous/Other
Comment Only
04/19/2024
Ducting rough in on 3rd floor first phase... approved
|
||||
Mechanical Final Inspection | Partial Pass | 5/21/2024 (12:30 - 2:30) | 5/21/2024 (PM) | 05/21/2024 |
Corrections:
Miscellaneous/Other
Resolved
05/21/2024
Balance report needed for 2nd floor of this remodel.
|
||||
Miscellaneous/Other
Carried Forward
05/21/2024
Balance reports needed for 2nd and 3rd floor areas.
|
||||
Miscellaneous/Other
Comment Only
05/21/2024
Viewed insulation and supply venting , with return air grates... approved
See outstanding comments for correction, send report to inspector. Jaaron@bloomingtonmn.gov
|
||||
Mechanical Final Inspection | Partial Pass | 8/1/2024 (10:00 - 12:00) | 8/1/2024 (AM) | 08/02/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
08/02/2024
Balance reports needed for 2nd and 3rd floor areas.
|
||||
Mechanical Rough-in Inspection | Passed | 8/13/2024 (10:00 - 12:00) | 8/13/2024 (AM) | 08/13/2024 |