Permit Application Status

PRMH202407934


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRMH202407934
Mechanical/HVAC
Finaled
SICK PRODUCT & COMPETENCE CENTER AMERICAS LLC
Other
Sick - Phase 2 - 4 story office tower mechanical scope
06/19/2024
07/08/2024
03/10/2026
09/11/2025

Locations

Permits

Permit Number: PRMH202407934

Mechanical
Finaled
07/08/2024
03/10/2026

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Final Inspection Pending
Mechanical Rough-in Inspection Partial Pass 12/30/2024 (8:00 - 10:00) 12/30/2024 (AM) 12/30/2024
Corrections:


Miscellaneous/Other
Carried Forward
12/30/2024
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers. 2 & 3 ready for duct insulation.

Mechanical Rough-in Inspection Partial Pass 1/14/2025 (8:00 - 10:00) 1/14/2025 (AM) 01/14/2025
Corrections:


Miscellaneous/Other
Carried Forward
01/14/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers. 2 & 3 ready for duct insulation.

Miscellaneous/Other
Carried Forward
01/14/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.

Mechanical Rough-in Inspection Partial Pass 1/30/2025 (10:00 - 12:00) 1/30/2025 (AM) 01/30/2025
Corrections:


Miscellaneous/Other
Carried Forward
01/30/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers. 2 & 3 ready for duct insulation.

Miscellaneous/Other
Carried Forward
01/30/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.

Miscellaneous/Other
Carried Forward
01/30/2025
2&3rd linear diffuser and 3 rd floor pass rough-in ready for duct insulation

Mechanical Rough-in Inspection Partial Pass 2/4/2025 (8:00 - 10:00) 2/4/2025 (AM) 02/04/2025
Corrections:


Miscellaneous/Other
Carried Forward
02/04/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers. 2 & 3 ready for duct insulation.

Miscellaneous/Other
Carried Forward
02/04/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.

Miscellaneous/Other
Carried Forward
02/04/2025
2&3rd linear diffuser and 3 rd floor pass rough-in ready for duct insulation

Miscellaneous/Other
Carried Forward
02/04/2025
2nd floor North, hydronic 100 PSI air test passed

Mechanical Rough-in Inspection Partial Pass 2/21/2025 (10:00 - 12:00) 2/21/2025 (AM) 02/24/2025
Corrections:


Miscellaneous/Other
Carried Forward
02/24/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers. 2 & 3 ready for duct insulation.

Miscellaneous/Other
Carried Forward
02/24/2025
2&3rd linear diffuser and 3 rd floor pass rough-in ready for duct insulation

Miscellaneous/Other
Carried Forward
02/24/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.

Miscellaneous/Other
Carried Forward
02/24/2025
2nd floor North, hydronic 100 PSI air test passed

Miscellaneous/Other
Carried Forward
02/24/2025
Water test grease duct from 2nd floor to roof, repairs completed and duct work is acceptable

Mechanical Rough-in Inspection Partial Pass 2/28/2025 (10:00 - 12:00) 2/28/2025 (AM) 02/28/2025
Corrections:


Miscellaneous/Other
Carried Forward
02/28/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers. 2 & 3 ready for duct insulation.

Miscellaneous/Other
Carried Forward
02/28/2025
2&3rd linear diffuser and 3 rd floor pass rough-in ready for duct insulation

Miscellaneous/Other
Carried Forward
02/28/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.

Miscellaneous/Other
Carried Forward
02/28/2025
2nd floor North, hydronic 100 PSI air test passed

Miscellaneous/Other
Carried Forward
02/28/2025
Water test grease duct from 2nd floor to roof, repairs completed and duct work is acceptable

Miscellaneous/Other
Carried Forward
02/28/2025
Do 2/28 2nd floor grease duct insulation pass. 1st floor south SM rough-in pass, ok to insulate.

Mechanical Rough-in Inspection Partial Pass 3/4/2025 (8:00 - 10:00) 3/4/2025 (AM) 03/04/2025
Corrections:


Miscellaneous/Other
Outstanding
02/28/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers. 2 & 3 ready for duct insulation.

Miscellaneous/Other
Outstanding
02/28/2025
2&3rd linear diffuser and 3 rd floor pass rough-in ready for duct insulation

Miscellaneous/Other
Outstanding
02/28/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.

Miscellaneous/Other
Outstanding
02/28/2025
2nd floor North, hydronic 100 PSI air test passed

Miscellaneous/Other
Outstanding
02/28/2025
Water test grease duct from 2nd floor to roof, repairs completed and duct work is acceptable

Miscellaneous/Other
Outstanding
02/28/2025
Do 2/28 2nd floor grease duct insulation pass. 1st floor south SM rough-in pass, ok to insulate.

Miscellaneous/Other
Outstanding
03/04/2025
3/4 grease duct insulation pass shaft pass and 100PSI test pass on 2nd floor southe runouts to heat pumps

Mechanical Rough-in Inspection Partial Pass 3/21/2025 (10:00 - 12:00) 3/21/2025 (AM) 03/21/2025
Corrections:


Miscellaneous/Other
Carried Forward
03/21/2025
1st floor duct continues installation and partial 3rd floor diffuser work

Mechanical Rough-in Inspection Partial Pass 4/11/2025 (10:00 - 12:00) 4/11/2025 (AM) 04/11/2025
Corrections:


Miscellaneous/Other
Carried Forward
04/11/2025
1st floor duct continues installation and partial 3rd floor diffuser work

Miscellaneous/Other
Carried Forward
04/11/2025
4/11- Sheetmetal on all 4 floors in different stage of finishing and piping air tests on geothermal piping for heat pumps on 4th, 2nd and 1st floor.

Mechanical Rough-in Inspection Partial Pass 4/22/2025 (12:30 - 2:30) 4/22/2025 (PM) 04/22/2025
Corrections:


Miscellaneous/Other
Carried Forward
04/22/2025
1st floor duct continues installation and partial 3rd floor diffuser work

Miscellaneous/Other
Carried Forward
04/22/2025
4/11- Sheetmetal on all 4 floors in different stage of finishing and piping air tests on geothermal piping for heat pumps on 4th, 2nd and 1st floor.

Miscellaneous/Other
Carried Forward
04/22/2025
4/22. Roof ductwork inspection passed,ready for insulation/clading. Mis ductwork on 1st floor. Excellent job

Mechanical Rough-in Inspection Partial Pass 5/5/2025 (8:00 - 10:00) 5/5/2025 (AM) 05/05/2025
Corrections:


Miscellaneous/Other
Carried Forward
05/05/2025
1st floor duct continues installation and partial 3rd floor diffuser work

Miscellaneous/Other
Carried Forward
05/05/2025
4/11- Sheetmetal on all 4 floors in different stage of finishing and piping air tests on geothermal piping for heat pumps on 4th, 2nd and 1st floor.

Miscellaneous/Other
Carried Forward
05/05/2025
4/22. Roof ductwork inspection passed,ready for insulation/clading. Mis ductwork on 1st floor. Excellent job

Miscellaneous/Other
Carried Forward
05/05/2025
5/5- Sheetmetal fill in different area to allow duct insulation and Sheetrock hard lids on 1st floor.

Mechanical Rough-in Inspection Partial Pass 5/27/2025 (12:30 - 2:30) 5/27/2025 (PM) 05/27/2025
Corrections:


Miscellaneous/Other
Carried Forward
05/27/2025
1st floor duct continues installation and partial 3rd floor diffuser work

Miscellaneous/Other
Carried Forward
05/27/2025
4/11- Sheetmetal on all 4 floors in different stage of finishing and piping air tests on geothermal piping for heat pumps on 4th, 2nd and 1st floor.

Miscellaneous/Other
Carried Forward
05/27/2025
4/22. Roof ductwork inspection passed,ready for insulation/clading. Mis ductwork on 1st floor. Excellent job

Miscellaneous/Other
Carried Forward
05/27/2025
5/5- Sheetmetal fill in different area to allow duct insulation and Sheetrock hard lids on 1st floor.

Miscellaneous/Other
Carried Forward
05/27/2025
5-27- 3rd floor above ceiling, 2nd floor diffusers and diffusers/ oval pipe on 1st floor

Mechanical Rough-in Inspection Passed 6/18/2025 (12:30 - 2:30) 6/18/2025 (PM) 06/24/2025
Corrections:


Miscellaneous/Other
Outstanding
05/27/2025
1st floor duct continues installation and partial 3rd floor diffuser work

Miscellaneous/Other
Outstanding
05/27/2025
4/11- Sheetmetal on all 4 floors in different stage of finishing and piping air tests on geothermal piping for heat pumps on 4th, 2nd and 1st floor.

Miscellaneous/Other
Outstanding
05/27/2025
4/22. Roof ductwork inspection passed,ready for insulation/clading. Mis ductwork on 1st floor. Excellent job

Miscellaneous/Other
Outstanding
05/27/2025
5/5- Sheetmetal fill in different area to allow duct insulation and Sheetrock hard lids on 1st floor.

Miscellaneous/Other
Outstanding
05/27/2025
5-27- 3rd floor above ceiling, 2nd floor diffusers and diffusers/ oval pipe on 1st floor

Mechanical Final Inspection Not Ready 7/11/2025 (12:30 - 2:30) 7/11/2025 (PM) 08/08/2025
Corrections:


Miscellaneous/Other
Carried Forward
08/08/2025
Multiple air test passes and final hydro approved. Gas line air test approved. Gas piping painted per code. Few items remaining. Final walkthrough in future

Mechanical Rough-in Inspection Passed 8/13/2025 (10:00 - 12:00) 8/13/2025 (AM) 08/13/2025
Corrections:


Miscellaneous/Other
Comment Only
08/13/2025
All diffusers and eggcrates are installed, and insulation completed for all above ceiling. Units installed at skyway, and above ceiling approved. Ok to cover remaining ceiling.

Mechanical Final Inspection Passed 9/3/2025 (10:00 - 12:00) 9/3/2025 (AM) 09/03/2025
Corrections:


Miscellaneous/Other
Resolved
09/03/2025
Multiple air test passes and final hydro approved. Gas line air test approved. Gas piping painted per code. Few items remaining. Final walkthrough in future

Miscellaneous/Other
Comment Only
09/03/2025
Tested hoods in kitchen.. approved Viewed smoke test in atrium, this test is pending fire inspection approval.

Mechanical Final Inspection Partial Pass 09/11/2025
Corrections:


Miscellaneous/Other
Comment Only
09/11/2025
Damper testing is completed and approved. Note... a retest of the atrium exhuast is pending, set up inspection with building and fire inspection. Balance report needed for this building for the permit final. This is a partial pass with the final inspection pending the above items.