PRMH202407934
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Final Inspection | Pending | |||
Mechanical Rough-in Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
04/22/2025
1st floor duct continues installation and partial 3rd floor diffuser work
|
||||
Miscellaneous/Other
Outstanding
04/22/2025
4/11- Sheetmetal on all 4 floors in different stage of finishing and piping air tests on geothermal piping for heat pumps on 4th, 2nd and 1st floor.
|
||||
Miscellaneous/Other
Outstanding
04/22/2025
4/22. Roof ductwork inspection passed,ready for insulation/clading. Mis ductwork on 1st floor. Excellent job
|
||||
Mechanical Rough-in Inspection | Partial Pass | 12/30/2024 (8:00 - 10:00) | 12/30/2024 (AM) | 12/30/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
12/30/2024
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers.
2 & 3 ready for duct insulation.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 1/14/2025 (8:00 - 10:00) | 1/14/2025 (AM) | 01/14/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
01/14/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers.
2 & 3 ready for duct insulation.
|
||||
Miscellaneous/Other
Carried Forward
01/14/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 1/30/2025 (10:00 - 12:00) | 1/30/2025 (AM) | 01/30/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
01/30/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers.
2 & 3 ready for duct insulation.
|
||||
Miscellaneous/Other
Carried Forward
01/30/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.
|
||||
Miscellaneous/Other
Carried Forward
01/30/2025
2&3rd linear diffuser and 3 rd floor pass rough-in ready for duct insulation
|
||||
Mechanical Rough-in Inspection | Partial Pass | 2/4/2025 (8:00 - 10:00) | 2/4/2025 (AM) | 02/04/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
02/04/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers.
2 & 3 ready for duct insulation.
|
||||
Miscellaneous/Other
Carried Forward
02/04/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.
|
||||
Miscellaneous/Other
Carried Forward
02/04/2025
2&3rd linear diffuser and 3 rd floor pass rough-in ready for duct insulation
|
||||
Miscellaneous/Other
Carried Forward
02/04/2025
2nd floor North, hydronic 100 PSI air test passed
|
||||
Mechanical Rough-in Inspection | Partial Pass | 2/21/2025 (10:00 - 12:00) | 2/21/2025 (AM) | 02/24/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
02/24/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers.
2 & 3 ready for duct insulation.
|
||||
Miscellaneous/Other
Carried Forward
02/24/2025
2&3rd linear diffuser and 3 rd floor pass rough-in ready for duct insulation
|
||||
Miscellaneous/Other
Carried Forward
02/24/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.
|
||||
Miscellaneous/Other
Carried Forward
02/24/2025
2nd floor North, hydronic 100 PSI air test passed
|
||||
Miscellaneous/Other
Carried Forward
02/24/2025
Water test grease duct from 2nd floor to roof, repairs completed and duct work is acceptable
|
||||
Mechanical Rough-in Inspection | Partial Pass | 2/28/2025 (10:00 - 12:00) | 2/28/2025 (AM) | 02/28/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
02/28/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers.
2 & 3 ready for duct insulation.
|
||||
Miscellaneous/Other
Carried Forward
02/28/2025
2&3rd linear diffuser and 3 rd floor pass rough-in ready for duct insulation
|
||||
Miscellaneous/Other
Carried Forward
02/28/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.
|
||||
Miscellaneous/Other
Carried Forward
02/28/2025
2nd floor North, hydronic 100 PSI air test passed
|
||||
Miscellaneous/Other
Carried Forward
02/28/2025
Water test grease duct from 2nd floor to roof, repairs completed and duct work is acceptable
|
||||
Miscellaneous/Other
Carried Forward
02/28/2025
Do 2/28 2nd floor grease duct insulation pass. 1st floor south SM rough-in pass, ok to insulate.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 3/4/2025 (8:00 - 10:00) | 3/4/2025 (AM) | 03/04/2025 |
Corrections:
Miscellaneous/Other
Outstanding
02/28/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers.
2 & 3 ready for duct insulation.
|
||||
Miscellaneous/Other
Outstanding
02/28/2025
2&3rd linear diffuser and 3 rd floor pass rough-in ready for duct insulation
|
||||
Miscellaneous/Other
Outstanding
02/28/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.
|
||||
Miscellaneous/Other
Outstanding
02/28/2025
2nd floor North, hydronic 100 PSI air test passed
|
||||
Miscellaneous/Other
Outstanding
02/28/2025
Water test grease duct from 2nd floor to roof, repairs completed and duct work is acceptable
|
||||
Miscellaneous/Other
Outstanding
02/28/2025
Do 2/28 2nd floor grease duct insulation pass. 1st floor south SM rough-in pass, ok to insulate.
|
||||
Miscellaneous/Other
Outstanding
03/04/2025
3/4 grease duct insulation pass shaft pass and 100PSI test pass on 2nd floor southe runouts to heat pumps
|
||||
Mechanical Rough-in Inspection | Partial Pass | 3/21/2025 (10:00 - 12:00) | 3/21/2025 (AM) | 03/21/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
03/21/2025
1st floor duct continues installation and partial 3rd floor diffuser work
|
||||
Mechanical Rough-in Inspection | Partial Pass | 4/11/2025 (10:00 - 12:00) | 4/11/2025 (AM) | 04/11/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
04/11/2025
1st floor duct continues installation and partial 3rd floor diffuser work
|
||||
Miscellaneous/Other
Carried Forward
04/11/2025
4/11- Sheetmetal on all 4 floors in different stage of finishing and piping air tests on geothermal piping for heat pumps on 4th, 2nd and 1st floor.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 4/22/2025 (12:30 - 2:30) | 4/22/2025 (PM) | 04/22/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
04/22/2025
1st floor duct continues installation and partial 3rd floor diffuser work
|
||||
Miscellaneous/Other
Carried Forward
04/22/2025
4/11- Sheetmetal on all 4 floors in different stage of finishing and piping air tests on geothermal piping for heat pumps on 4th, 2nd and 1st floor.
|
||||
Miscellaneous/Other
Carried Forward
04/22/2025
4/22. Roof ductwork inspection passed,ready for insulation/clading. Mis ductwork on 1st floor. Excellent job
|