Permit Application Status

PRMH202407934


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRMH202407934
Mechanical/HVAC
Permit(s) Issued
SICK PRODUCT & COMPETENCE CENTER AMERICAS LLC
Other
Sick - Phase 2 - 4 story office tower mechanical scope
06/19/2024
07/08/2024
10/19/2025

Locations

Permits

Permit Number: PRMH202407934

Mechanical
Issued
07/08/2024
10/19/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Final Inspection Pending
Mechanical Rough-in Inspection Pending
Corrections:


Miscellaneous/Other
Outstanding
04/22/2025
1st floor duct continues installation and partial 3rd floor diffuser work

Miscellaneous/Other
Outstanding
04/22/2025
4/11- Sheetmetal on all 4 floors in different stage of finishing and piping air tests on geothermal piping for heat pumps on 4th, 2nd and 1st floor.

Miscellaneous/Other
Outstanding
04/22/2025
4/22. Roof ductwork inspection passed,ready for insulation/clading. Mis ductwork on 1st floor. Excellent job

Mechanical Rough-in Inspection Partial Pass 12/30/2024 (8:00 - 10:00) 12/30/2024 (AM) 12/30/2024
Corrections:


Miscellaneous/Other
Carried Forward
12/30/2024
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers. 2 & 3 ready for duct insulation.

Mechanical Rough-in Inspection Partial Pass 1/14/2025 (8:00 - 10:00) 1/14/2025 (AM) 01/14/2025
Corrections:


Miscellaneous/Other
Carried Forward
01/14/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers. 2 & 3 ready for duct insulation.

Miscellaneous/Other
Carried Forward
01/14/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.

Mechanical Rough-in Inspection Partial Pass 1/30/2025 (10:00 - 12:00) 1/30/2025 (AM) 01/30/2025
Corrections:


Miscellaneous/Other
Carried Forward
01/30/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers. 2 & 3 ready for duct insulation.

Miscellaneous/Other
Carried Forward
01/30/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.

Miscellaneous/Other
Carried Forward
01/30/2025
2&3rd linear diffuser and 3 rd floor pass rough-in ready for duct insulation

Mechanical Rough-in Inspection Partial Pass 2/4/2025 (8:00 - 10:00) 2/4/2025 (AM) 02/04/2025
Corrections:


Miscellaneous/Other
Carried Forward
02/04/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers. 2 & 3 ready for duct insulation.

Miscellaneous/Other
Carried Forward
02/04/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.

Miscellaneous/Other
Carried Forward
02/04/2025
2&3rd linear diffuser and 3 rd floor pass rough-in ready for duct insulation

Miscellaneous/Other
Carried Forward
02/04/2025
2nd floor North, hydronic 100 PSI air test passed

Mechanical Rough-in Inspection Partial Pass 2/21/2025 (10:00 - 12:00) 2/21/2025 (AM) 02/24/2025
Corrections:


Miscellaneous/Other
Carried Forward
02/24/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers. 2 & 3 ready for duct insulation.

Miscellaneous/Other
Carried Forward
02/24/2025
2&3rd linear diffuser and 3 rd floor pass rough-in ready for duct insulation

Miscellaneous/Other
Carried Forward
02/24/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.

Miscellaneous/Other
Carried Forward
02/24/2025
2nd floor North, hydronic 100 PSI air test passed

Miscellaneous/Other
Carried Forward
02/24/2025
Water test grease duct from 2nd floor to roof, repairs completed and duct work is acceptable

Mechanical Rough-in Inspection Partial Pass 2/28/2025 (10:00 - 12:00) 2/28/2025 (AM) 02/28/2025
Corrections:


Miscellaneous/Other
Carried Forward
02/28/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers. 2 & 3 ready for duct insulation.

Miscellaneous/Other
Carried Forward
02/28/2025
2&3rd linear diffuser and 3 rd floor pass rough-in ready for duct insulation

Miscellaneous/Other
Carried Forward
02/28/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.

Miscellaneous/Other
Carried Forward
02/28/2025
2nd floor North, hydronic 100 PSI air test passed

Miscellaneous/Other
Carried Forward
02/28/2025
Water test grease duct from 2nd floor to roof, repairs completed and duct work is acceptable

Miscellaneous/Other
Carried Forward
02/28/2025
Do 2/28 2nd floor grease duct insulation pass. 1st floor south SM rough-in pass, ok to insulate.

Mechanical Rough-in Inspection Partial Pass 3/4/2025 (8:00 - 10:00) 3/4/2025 (AM) 03/04/2025
Corrections:


Miscellaneous/Other
Outstanding
02/28/2025
12/30- 2nd & 3rd floor rough in duct complete and 3rd partial & 4th risers. 2 & 3 ready for duct insulation.

Miscellaneous/Other
Outstanding
02/28/2025
2&3rd linear diffuser and 3 rd floor pass rough-in ready for duct insulation

Miscellaneous/Other
Outstanding
02/28/2025
1/14- All shaft duct insulation pass. 2nd and 3rd progress rough-in looks great.

Miscellaneous/Other
Outstanding
02/28/2025
2nd floor North, hydronic 100 PSI air test passed

Miscellaneous/Other
Outstanding
02/28/2025
Water test grease duct from 2nd floor to roof, repairs completed and duct work is acceptable

Miscellaneous/Other
Outstanding
02/28/2025
Do 2/28 2nd floor grease duct insulation pass. 1st floor south SM rough-in pass, ok to insulate.

Miscellaneous/Other
Outstanding
03/04/2025
3/4 grease duct insulation pass shaft pass and 100PSI test pass on 2nd floor southe runouts to heat pumps

Mechanical Rough-in Inspection Partial Pass 3/21/2025 (10:00 - 12:00) 3/21/2025 (AM) 03/21/2025
Corrections:


Miscellaneous/Other
Carried Forward
03/21/2025
1st floor duct continues installation and partial 3rd floor diffuser work

Mechanical Rough-in Inspection Partial Pass 4/11/2025 (10:00 - 12:00) 4/11/2025 (AM) 04/11/2025
Corrections:


Miscellaneous/Other
Carried Forward
04/11/2025
1st floor duct continues installation and partial 3rd floor diffuser work

Miscellaneous/Other
Carried Forward
04/11/2025
4/11- Sheetmetal on all 4 floors in different stage of finishing and piping air tests on geothermal piping for heat pumps on 4th, 2nd and 1st floor.

Mechanical Rough-in Inspection Partial Pass 4/22/2025 (12:30 - 2:30) 4/22/2025 (PM) 04/22/2025
Corrections:


Miscellaneous/Other
Carried Forward
04/22/2025
1st floor duct continues installation and partial 3rd floor diffuser work

Miscellaneous/Other
Carried Forward
04/22/2025
4/11- Sheetmetal on all 4 floors in different stage of finishing and piping air tests on geothermal piping for heat pumps on 4th, 2nd and 1st floor.

Miscellaneous/Other
Carried Forward
04/22/2025
4/22. Roof ductwork inspection passed,ready for insulation/clading. Mis ductwork on 1st floor. Excellent job