PRMH202408417
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Rough-in Inspection | Partial Pass | 10/15/2024 (10:00 - 12:00) | 10/15/2024 (AM) | 10/16/2024 |
|
Corrections:
Miscellaneous/Other
Carried Forward
10/16/2024
10/15 Sheetmetal rough in passed
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 10/17/2024 (2:30 - 3:30) | 10/17/2024 (PM) | 10/17/2024 |
|
Corrections:
Miscellaneous/Other
Carried Forward
10/17/2024
10/15 Sheetmetal rough in passed
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 10/28/2024 (12:30 - 2:30) | 10/28/2024 (PM) | 10/29/2024 |
|
Corrections:
Miscellaneous/Other
Carried Forward
10/29/2024
10/15 Sheetmetal rough in passed
|
||||
| Mechanical Final Inspection | Partial Pass | 11/15/2024 (10:00 - 12:00) | 11/15/2024 (AM) | 11/15/2024 |
|
Corrections:
Miscellaneous/Other
Carried Forward
11/15/2024
Heating piping hydro passed, chilled water will be flushed,finished and hydroed. HVAC system in computer room has issues
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 11/15/2024 (10:00 - 12:00) | 11/15/2024 (AM) | 11/15/2024 |
|
Corrections:
Miscellaneous/Other
Carried Forward
11/15/2024
10/15 Sheetmetal rough in passed, 11/15 heating pipe passed chilled piping and HVAC issues outstanding, but progressing.
|
||||
| Mechanical Rough-in Inspection | Passed | 12/9/2024 (8:00 - 10:00) | 12/9/2024 (AM) | 12/09/2024 |
|
Corrections:
Miscellaneous/Other
Outstanding
11/15/2024
10/15 Sheetmetal rough in passed, 11/15 heating pipe passed chilled piping and HVAC issues outstanding, but progressing.
|
||||
| Mechanical Final Inspection | Passed | 1/30/2025 (8:00 - 10:00) | 1/30/2025 (AM) | 01/30/2025 |
| Really nice job by MMC | ||||
|
Corrections:
Miscellaneous/Other
Outstanding
11/15/2024
Heating piping hydro passed, chilled water will be flushed,finished and hydroed. HVAC system in computer room has issues
|
||||