PRMH202408528
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Partial Pass | 10/3/2024 (10:00 - 12:00) | 10/3/2024 (AM) | 10/07/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
10/07/2024
4th floor Mock up passed and 10 4th floor rooms passes
|
||||
Mechanical Rough-in Inspection | Partial Pass | 10/8/2024 (2:30 - 3:30) | 10/8/2024 (PM) | 10/10/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
10/10/2024
4th floor Mock up passed and 10 4th floor rooms passes. 10/7-4th floor phase 1 rough-in pass inspection
|
||||
Mechanical Rough-in Inspection | Partial Pass | 10/15/2024 (10:00 - 12:00) | 10/15/2024 (AM) | 10/16/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
10/16/2024
4th floor Mock up passed and 10 4th floor rooms passes. 10/7-4th floor phase 1 rough-in pass inspection
|
||||
Miscellaneous/Other
Carried Forward
10/16/2024
10/15 4th floor phase 2 rough in passed
|
||||
Mechanical Rough-in Inspection | Partial Pass | 10/18/2024 (8:00 - 10:00) | 10/18/2024 (AM) | 10/21/2024 |
Corrections:
Miscellaneous/Other
Outstanding
10/16/2024
4th floor Mock up passed and 10 4th floor rooms passes. 10/7-4th floor phase 1 rough-in pass inspection
|
||||
Miscellaneous/Other
Outstanding
10/16/2024
10/15 4th floor phase 2 rough in passed
|
||||
Miscellaneous/Other
Outstanding
10/21/2024
Soffit duct work inspection pass 10/17
|
||||
Mechanical Rough-in Inspection | Partial Pass | 10/21/2024 (10:00 - 12:00) | 10/21/2024 (AM) | 10/23/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
10/28/2024
3rd floor dryer and exhaust vents need more looking into and fire caulk not complete
|
||||
Mechanical Rough-in Inspection | Partial Pass | 10/24/2024 (Morning) | 10/24/2024 (AM) | 10/30/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
11/06/2024
10/24 3rd floor fire caulk passed and dryer/bath fan exhaust passed
|
||||
Mechanical Rough-in Inspection | Partial Pass | 10/30/2024 (2:30 - 3:30) | 10/30/2024 (PM) | 11/06/2024 |
Corrections:
Miscellaneous/Other
Outstanding
10/28/2024
3rd floor dryer and exhaust vents need more looking into and fire caulk not complete 10/30 soffit duct pass and 3rd fire caulk pass
|
||||
Mechanical Rough-in Inspection | Partial Pass | 11/7/2024 (10:00 - 12:00) | 11/7/2024 (AM) | 11/07/2024 |
Corrections:
Miscellaneous/Other
Outstanding
11/06/2024
10/24 3rd floor fire caulk passed and dryer/bath fan exhaust passed. 3rd floor soffit pass 11/7
|
||||
Mechanical Rough-in Inspection | Partial Pass | 11/12/2024 (2:30 - 3:30) | 11/12/2024 (PM) | 11/13/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
11/13/2024
11/12 3rd floor soffit inspection pass
|
||||
Mechanical Rough-in Inspection | Partial Pass | 11/19/2024 (10:00 - 12:00) | 11/19/2024 (AM) | 11/19/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
11/19/2024
11/12 3rd floor soffit inspection pass
|
||||
Miscellaneous/Other
Carried Forward
11/19/2024
11/9-1st floor dryer and exhaust fire caulk inspection passed and pvc condensate pipe fire caulk passed
|
||||
Mechanical Rough-in Inspection | Partial Pass | 11/22/2024 (8:00 - 10:00) | 11/22/2024 (AM) | 11/22/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
11/22/2024
11/12 3rd floor soffit inspection pass
|
||||
Miscellaneous/Other
Carried Forward
11/22/2024
11/9-1st floor dryer and exhaust fire caulk inspection passed and pvc condensate pipe fire caulk passed
|
||||
Miscellaneous/Other
Carried Forward
11/22/2024
11/22 soffit inspection west 2nd floor passed
|
||||
Mechanical Rough-in Inspection | Partial Pass | 12/2/2024 (8:00 - 10:00) | 12/2/2024 (AM) | 12/02/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
12/10/2024
West 2nd floor soffit duct is good to go
|
||||
Mechanical Rough-in Inspection | Partial Pass | 12/10/2024 (8:00 - 10:00) | 12/10/2024 (AM) | 12/10/2024 |
Corrections:
Miscellaneous/Other
Outstanding
11/22/2024
11/12 3rd floor soffit inspection pass
|
||||
Miscellaneous/Other
Outstanding
11/22/2024
11/9-1st floor dryer and exhaust fire caulk inspection passed and pvc condensate pipe fire caulk passed
|
||||
Miscellaneous/Other
Outstanding
11/22/2024
11/22 soffit inspection west 2nd floor passed and riser shaft rough in and garbage venting pass.
|
||||
Miscellaneous/Other
Outstanding
12/10/2024
12/10 1st floor soffit inspection pass Riser shaft and garbage exhaust insulation pass.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 12/19/2024 (8:00 - 10:00) | 12/19/2024 (AM) | 12/19/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
12/19/2024
West 2nd floor soffit duct is good to go
|
||||
Miscellaneous/Other
Carried Forward
12/19/2024
12/19-1st floor west soffit inspection pass
|
||||
Mechanical Rough-in Inspection | Partial Pass | 1/8/2025 (8:00 - 10:00) | 1/8/2025 (AM) | 01/08/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
01/08/2025
West 2nd floor soffit duct is good to go
|
||||
Miscellaneous/Other
Carried Forward
01/08/2025
12/19-1st floor west soffit inspection pass
|
||||
Miscellaneous/Other
Carried Forward
01/08/2025
1/8- rough-in inspection of ductwork in common area 1st floor. 30 psi air test on gas piping in underground parking garage-pass. 50 psi air test on snowmelt piping-pass
|
||||
Mechanical Final Inspection | Partial Pass | 2/27/2025 (10:00 - 12:00) | 2/27/2025 (AM) | 02/27/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
02/27/2025
2/27 All apt units bath exhaust, heat pumps and dryer venting I could see are all pass, More inspections to come.
|
||||
Mechanical Rough-in Inspection | Passed | 03/19/2025 | ||
Corrections:
Miscellaneous/Other
Outstanding
01/08/2025
West 2nd floor soffit duct is good to go
|
||||
Miscellaneous/Other
Outstanding
01/08/2025
12/19-1st floor west soffit inspection pass
|
||||
Miscellaneous/Other
Outstanding
01/08/2025
1/8- rough-in inspection of ductwork in common area 1st floor. 30 psi air test on gas piping in underground parking garage-pass. 50 psi air test on snowmelt piping-pass
|
||||
Mechanical Final Inspection | Passed | 3/11/2025 (10:00 - 12:00) | 3/11/2025 (AM) | 03/19/2025 |
Corrections:
Miscellaneous/Other
Outstanding
02/27/2025
2/27 All apt units bath exhaust, heat pumps and dryer venting I could see are all pass, More inspections to come.
|
||||
Miscellaneous/Other
Outstanding
03/11/2025
Underground parking CO detectors/fan test passed. Smoke fire damper test passed on hallways. Underground parking visual ok Except for hanger on west unit heater flue and relief discharge on snowmelt boiler. Balance reports coming. Very nice job
|