PRMH202413102
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Final Inspection | Pending | |||
| Mechanical Rough-in Inspection | Partial Pass | 4/2/2025 (10:00 - 12:00) | 4/2/2025 (AM) | 04/03/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
04/03/2025
Consult few apt exhaust points are less than 10’ from air intake but are < 9’ almost 10’ on diagonal. Exhaust has no byproducts of combustion. Acceptable for variance/no hazard
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 5/21/2025 (10:00 - 12:00) | 5/21/2025 (AM) | 05/21/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
04/03/2025
Consult few apt exhaust points are less than 10’ from air intake but are < 9’ almost 10’ on diagonal. Exhaust has no byproducts of combustion. Acceptable for variance/no hazard
|
||||
|
Miscellaneous/Other
Outstanding
05/21/2025
5/21- Rough in pass on 5th floor East side. Ready for insulation/vapor barrier.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 5/22/2025 (10:00 - 12:00) | 5/22/2025 (AM) | 05/22/2025 |
| Mechanical Rough-in Inspection | Partial Pass | 6/5/2025 (10:00 - 12:00) | 6/5/2025 (AM) | 06/06/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
06/06/2025
6/5- 5th floor west rough in pass, ready for insulation.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 6/17/2025 (2:30 - 3:30) | 6/17/2025 (PM) | 06/17/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
06/24/2025
6/5- 5th floor west rough in pass, ready for insulation.
|
||||
|
Miscellaneous/Other
Carried Forward
06/24/2025
6/17-5th floor east sheet metal inspection before soffit install 4end rooms not complete signed on door inspection sheet.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 6/18/2025 (2:30 - 3:30) | 6/18/2025 (PM) | 07/02/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
07/02/2025
6/18- 5th floor rough in. Partial pass
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 6/24/2025 (12:30 - 2:30) | 6/24/2025 (PM) | 07/03/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
06/24/2025
6/5- 5th floor west rough in pass, ready for insulation.
|
||||
|
Miscellaneous/Other
Outstanding
06/24/2025
6/17-5th floor east sheet metal inspection before soffit install 4end rooms not complete signed on door inspection sheet.
|
||||
|
Miscellaneous/Other
Outstanding
07/03/2025
6/24- 5th floor rough in pass except 501,502 and 504
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/1/2025 (8:00 - 10:00) | 7/1/2025 (AM) | 07/03/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
07/03/2025
Unit 427 trash exhaust rough in and insulation pass. West 4th floor partial pass.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/2/2025 (2:30 - 3:30) | 7/2/2025 (PM) | 07/03/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
07/03/2025
5th floor sheetmetal inspection sign off for soffits.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/3/2025 (2:30 - 3:30) | 7/3/2025 (PM) | 07/03/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
07/14/2025
6/18- 5th floor rough in. Partial pass
|
||||
|
Miscellaneous/Other
Carried Forward
07/14/2025
7/3 Sheetmetal sign off of 5th floor completed.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/15/2025 (8:00 - 10:00) | 7/15/2025 (AM) | 07/15/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
07/15/2025
4th floor rough in and 4th floor sheetmetal rough in for soffits
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/16/2025 (12:30 - 2:30) | 7/16/2025 (PM) | 07/17/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
07/21/2025
6/18- 5th floor rough in. Partial pass
|
||||
|
Miscellaneous/Other
Carried Forward
07/21/2025
7/3 Sheetmetal sign off of 5th floor completed.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/17/2025 (12:30 - 2:30) | 7/17/2025 (PM) | 08/08/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
08/08/2025
5th floor soffit inspection pass
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/22/2025 (12:30 - 2:30) | 7/22/2025 (PM) | 08/08/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
07/21/2025
6/18- 5th floor rough in. Partial pass
|
||||
|
Miscellaneous/Other
Outstanding
07/21/2025
7/3 Sheetmetal sign off of 5th floor completed.
|
||||
|
Miscellaneous/Other
Outstanding
08/08/2025
7/22- 4th floor soffit
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/23/2025 (12:30 - 2:30) | 7/23/2025 (PM) | 08/08/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
08/08/2025
7/23-4th and 1st floor soffits
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/24/2025 (8:00 - 10:00) | 7/24/2025 (AM) | 08/08/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
08/08/2025
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/28/2025 (12:30 - 2:30) | 7/28/2025 (PM) | 08/08/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
08/08/2025
3rd floor 1st rough in inspection
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/29/2025 (12:30 - 2:30) | 7/29/2025 (PM) | 08/08/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
08/08/2025
Not ready today
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 8/5/2025 (10:00 - 12:00) | 8/5/2025 (AM) | 08/08/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
08/08/2025
8/5-2nd dollar 1st rough in
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 8/6/2025 (10:00 - 12:00) | 8/6/2025 (AM) | 08/08/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
08/18/2025
Fire damper walk-check code compliance
|
||||
| Mechanical Rough-in Inspection | Passed | 8/11/2025 (12:30 - 2:30) | 8/11/2025 (PM) | 08/11/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/11/2025
supply's and combustion air intake ducting for units of 3rd floor area A.... approved
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 8/19/2025 (10:00 - 12:00) | 8/19/2025 (AM) | 08/19/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/19/2025
Inspection of rough work on a portion of units on second floor okay. Inspection of above ceiling connection on a portion of fan coils okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 8/20/2025 (2:30 - 3:30) | 8/20/2025 (PM) | 08/20/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/20/2025
Inspection of rough work for portion of units on second floor okay. Inspection of portion of soffit ducting on units on 3rd floor okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 8/21/2025 (8:00 - 10:00) | 8/21/2025 (AM) | 08/21/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/21/2025
Inspection of soffit ducting on remaining units on 3rd floor okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 9/2/2025 (12:30 - 2:30) | 9/2/2025 (PM) | 09/02/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/02/2025
Visual inspection on above ceiling fan coils on 3rd floor okay. Rough inspection on a portion of units of the east side of 1st floor okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 9/3/2025 (10:00 - 12:00) | 9/3/2025 (AM) | 09/03/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/03/2025
Visual inspection of a portion unit rough in’s on 1st floor on the west side of building okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 9/4/2025 (8:00 - 10:00) | 9/4/2025 (AM) | 09/04/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/04/2025
Inspection of rough work in remaining 1st floor units and common areas on 1st floor okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 9/8/2025 (10:00 - 12:00) | 9/8/2025 (AM) | 09/08/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/08/2025
Inspection of a portion of unit soffit ducting on 2nd floor of East side of the building okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 9/10/2025 (8:00 - 10:00) | 9/10/2025 (AM) | 09/10/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/10/2025
Inspection of soffit ducting on a portion of units on the 2nd floor is n the East side of the building okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 9/11/2025 (8:00 - 10:00) | 9/11/2025 (AM) | 09/11/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/11/2025
Inspection of a portion of 2nd floor units soffit ducting okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 9/16/2025 (10:00 - 12:00) | 9/16/2025 (AM) | 09/16/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/16/2025
Inspection of soffit ducting on remaining units on the west side of the 2nd floor okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 9/17/2025 (2:30 - 3:30) | 9/17/2025 (PM) | 09/17/2025 |
| Mechanical Rough-in Inspection | Partial Pass | 9/29/2025 (10:00 - 12:00) | 9/29/2025 (AM) | 09/29/2025 |
| Same Day | ||||
| Mechanical Rough-in Inspection | Partial Pass | 10/2/2025 (8:00 - 10:00) | 10/2/2025 (AM) | 10/02/2025 |
| Mechanical Rough-in Inspection | Partial Pass | 10/7/2025 (8:00 - 10:00) | 10/7/2025 (AM) | 10/07/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/07/2025
Inspection of soffit ducting on a portion of units on the 1st floor west side of building okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 10/7/2025 (2:30 - 3:30) | 10/7/2025 (PM) | 10/07/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/07/2025
Air tests for a portion of the csst gas risers okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 10/13/2025 (8:00 - 10:00) | 10/13/2025 (AM) | 10/13/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/13/2025
Air test for a portion of gas lines okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 10/14/2025 (10:00 - 12:00) | 10/14/2025 (AM) | 10/14/2025 |
| Same day inspection, Ok by Dave [Resler\, Megan @ 10/14/2025 11:21 AM] | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
10/14/2025
Air tests on a portion of gas risers okay.
|
||||
|
Miscellaneous/Other
Comment Only
10/14/2025
Air tests on a portion of gas risers okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 10/15/2025 (8:00 - 10:00) | 10/15/2025 (AM) | 10/15/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/15/2025
Inspection of first floor west side fan coils in units okay. Air tests for a portion of gas risers okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 10/16/2025 | 10/16/2025 (AM) | 10/16/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/16/2025
Air test on a portion of gas risers okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 10/20/2025 (8:00 - 10:00) | 10/20/2025 (AM) | 10/20/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/20/2025
Air tests on a portion of gas risers okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 10/20/2025 (2:30 - 3:30) | 10/20/2025 (PM) | 10/20/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/20/2025
Air tests on remaining gas risers on west side of building ok.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 10/28/2025 (12:30 - 2:30) | 10/28/2025 (PM) | 10/28/2025 |
| Mechanical Rough-in Inspection | Partial Pass | 10/30/2025 (8:00 - 10:00) | 10/30/2025 (AM) | 10/30/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/30/2025
Visual inspection of 1st floor common area soffit ducting and fan coil units okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 11/6/2025 (12:30 - 2:30) | 11/6/2025 (PM) | 11/06/2025 |
| Mechanical Rough-in Inspection | Partial Pass | 11/10/2025 (8:00 - 10:00) | 11/10/2025 (AM) | 11/10/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/10/2025
Air test for a portion of gas risers on the west side of building okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 11/12/2025 (12:30 - 2:30) | 11/12/2025 (PM) | 11/12/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/12/2025
Air tests on remaining gas risers for units on west side of building okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 11/13/2025 (8:00 - 10:00) | 11/13/2025 (AM) | 11/13/2025 |
| Mechanical Final Inspection | Partial Pass | 1/26/2026 (10:00 - 12:00) | 1/26/2026 (AM) | 01/26/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/26/2026
Final inspection of 5th and 4th floor units okay.
|
||||
| Mechanical Final Inspection | Partial Pass | 01/28/2026 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
01/28/2026
Final inspection of 3rd floor units okay.
|
||||
| Mechanical Final Inspection | Partial Pass | 2/17/2026 (8:00 - 10:00) | 2/17/2026 (AM) | 02/17/2026 |
| Inspect 1-3 floors | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
02/17/2026
Final inspection of units on 1st and 2nd floor okay.
|
||||
| Mechanical Final Inspection | Partial Pass | 2/18/2026 (8:00 - 10:00) | 2/18/2026 (AM) | 02/18/2026 |
| Gas main air test | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
02/18/2026
Visual inspection and air test of 2 psi gas main okay. Inspection of garage heaters and venting okay. Still has gas work on patio to be completed and inspected.
|
||||
| Mechanical Final Inspection | Partial Pass | 3/3/2026 (8:00 - 10:00) | 3/3/2026 (AM) | 03/03/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/03/2026
Inspection of common area's on 1st floor okay. Inspection of roof top equipment okay, but contractor needs to change out vent limiters on regulators and swap split rings on gas piping serving rtu's to galvanized. Contractor to still label all gas piping in garage, and provide test of exhaust system in garage, rtu's, and dampers.
|
||||
| Mechanical Final Inspection | Partial Pass | 3/4/2026 (8:00 - 10:00) | 3/4/2026 (AM) | 03/04/2026 |
| smoke dampers | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
03/04/2026
Inspection of all fire and smoke dampers okay.
|
||||
| Mechanical Final Inspection | Partial Pass | 3/12/2026 (8:00 - 10:00) | 3/12/2026 (AM) | 03/12/2026 |
| Garage | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
03/12/2026
Inspection and testing of parking garage exhaust system okay. All labeling of gas piping in garage has been completed. Will still need to inspect work yet to be completed in courtyard area.
|
||||