PRMH202414207
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Final Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
05/13/2025
5/7- P-1 Pass, waiting for balance reports, P-3 not ready.
|
||||
Mechanical Rough-in Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
06/04/2025
5/12- P-1. 100 PSI air test pass on VAV’s and one AHU. P-3. All fusion welded pipe/AHU tested 100 PSI Hydrostatic test. Passed
|
||||
Miscellaneous/Other
Outstanding
06/04/2025
5/22- 100 PSI hydrostatic test on chilled water piping in P-3 building. Upper floor mechanical room. Pass
|
||||
Miscellaneous/Other
Outstanding
06/04/2025
6/4- P-3 100 PSI Hydrostatic test on MUA heating piping in penthouse. 3 PSI test on nitrogen piping and industrial waste piping order floor PASS
|
||||
Mechanical Rough-in Inspection | Partial Pass | 2/18/2025 (10:00 - 12:00) | 2/18/2025 (AM) | 02/26/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
02/26/2025
Geothermal 1st floor mains,2nd&3rd floor risers/mains.
5-psi gas boiler room adjacent to 4th floor deck.
2-psi gas boiler room adjacent to kitchen-Very nice job
|
||||
Mechanical Rough-in Inspection | Partial Pass | 4/10/2025 (8:00 - 10:00) | 4/10/2025 (AM) | 04/10/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
04/10/2025
Geothermal 1st floor mains,2nd&3rd floor risers/mains.
5-psi gas boiler room adjacent to 4th floor deck.
2-psi gas boiler room adjacent to kitchen-Very nice job
|
||||
Miscellaneous/Other
Carried Forward
04/10/2025
4/10- Chilled water piping hydro test 100 PSI
|
||||
Mechanical Rough-in Inspection | Partial Pass | 5/9/2025 (8:00 - 10:00) | 5/9/2025 (AM) | 05/13/2025 |
Corrections:
Miscellaneous/Other
Outstanding
04/10/2025
Geothermal 1st floor mains,2nd&3rd floor risers/mains.
5-psi gas boiler room adjacent to 4th floor deck.
2-psi gas boiler room adjacent to kitchen-Very nice job
|
||||
Miscellaneous/Other
Outstanding
04/10/2025
4/10- Chilled water piping hydro test 100 PSI
|
||||
Miscellaneous/Other
Outstanding
05/13/2025
5/9- P-1 pass and P-3 partial pass. Need balance report for P-1
|
||||
Mechanical Final Inspection | Partial Pass | 5/9/2025 (8:00 - 10:00) | 5/9/2025 (AM) | 05/13/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
05/13/2025
5/7- P-1 Pass, waiting for balance reports, P-3 not ready.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 5/12/2025 (12:30 - 2:30) | 5/12/2025 (PM) | 05/13/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
05/13/2025
5/12- P-1. 100 PSI air test pass on VAV’s and one AHU. P-3. All fusion welded pipe/AHU tested 100 PSI Hydrostatic test. Passed
|
||||
Mechanical Rough-in Inspection | Partial Pass | 5/22/2025 (10:00 - 12:00) | 5/22/2025 (AM) | 05/22/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
05/22/2025
5/12- P-1. 100 PSI air test pass on VAV’s and one AHU. P-3. All fusion welded pipe/AHU tested 100 PSI Hydrostatic test. Passed
|
||||
Miscellaneous/Other
Carried Forward
05/22/2025
5/22- 100 PSI hydrostatic test on chilled water piping in P-3 building. Upper floor mechanical room. Pass
|
||||
Mechanical Rough-in Inspection | Partial Pass | 6/4/2025 (8:00 - 10:00) | 6/4/2025 (AM) | 06/04/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
06/04/2025
5/12- P-1. 100 PSI air test pass on VAV’s and one AHU. P-3. All fusion welded pipe/AHU tested 100 PSI Hydrostatic test. Passed
|
||||
Miscellaneous/Other
Carried Forward
06/04/2025
5/22- 100 PSI hydrostatic test on chilled water piping in P-3 building. Upper floor mechanical room. Pass
|
||||
Miscellaneous/Other
Carried Forward
06/04/2025
6/4- P-3 100 PSI Hydrostatic test on MUA heating piping in penthouse. 3 PSI test on nitrogen piping and industrial waste piping order floor PASS
|