PRMH202414207
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Final Inspection | Pending | |||
| Mechanical Rough-in Inspection | Partial Pass | 2/18/2025 (10:00 - 12:00) | 2/18/2025 (AM) | 02/26/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
02/26/2025
Geothermal 1st floor mains,2nd&3rd floor risers/mains.
5-psi gas boiler room adjacent to 4th floor deck.
2-psi gas boiler room adjacent to kitchen-Very nice job
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 4/10/2025 (8:00 - 10:00) | 4/10/2025 (AM) | 04/10/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
04/10/2025
Geothermal 1st floor mains,2nd&3rd floor risers/mains.
5-psi gas boiler room adjacent to 4th floor deck.
2-psi gas boiler room adjacent to kitchen-Very nice job
|
||||
|
Miscellaneous/Other
Carried Forward
04/10/2025
4/10- Chilled water piping hydro test 100 PSI
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 5/9/2025 (8:00 - 10:00) | 5/9/2025 (AM) | 05/13/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
04/10/2025
Geothermal 1st floor mains,2nd&3rd floor risers/mains.
5-psi gas boiler room adjacent to 4th floor deck.
2-psi gas boiler room adjacent to kitchen-Very nice job
|
||||
|
Miscellaneous/Other
Outstanding
04/10/2025
4/10- Chilled water piping hydro test 100 PSI
|
||||
|
Miscellaneous/Other
Outstanding
05/13/2025
5/9- P-1 pass and P-3 partial pass. Need balance report for P-1
|
||||
| Mechanical Final Inspection | Partial Pass | 5/9/2025 (8:00 - 10:00) | 5/9/2025 (AM) | 05/13/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
05/13/2025
5/7- P-1 Pass, waiting for balance reports, P-3 not ready.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 5/12/2025 (12:30 - 2:30) | 5/12/2025 (PM) | 05/13/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
05/13/2025
5/12- P-1. 100 PSI air test pass on VAV’s and one AHU. P-3. All fusion welded pipe/AHU tested 100 PSI Hydrostatic test. Passed
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 5/22/2025 (10:00 - 12:00) | 5/22/2025 (AM) | 05/22/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
05/22/2025
5/12- P-1. 100 PSI air test pass on VAV’s and one AHU. P-3. All fusion welded pipe/AHU tested 100 PSI Hydrostatic test. Passed
|
||||
|
Miscellaneous/Other
Carried Forward
05/22/2025
5/22- 100 PSI hydrostatic test on chilled water piping in P-3 building. Upper floor mechanical room. Pass
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 6/4/2025 (8:00 - 10:00) | 6/4/2025 (AM) | 06/04/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
06/04/2025
5/12- P-1. 100 PSI air test pass on VAV’s and one AHU. P-3. All fusion welded pipe/AHU tested 100 PSI Hydrostatic test. Passed
|
||||
|
Miscellaneous/Other
Carried Forward
06/04/2025
5/22- 100 PSI hydrostatic test on chilled water piping in P-3 building. Upper floor mechanical room. Pass
|
||||
|
Miscellaneous/Other
Carried Forward
06/04/2025
6/4- P-3 100 PSI Hydrostatic test on MUA heating piping in penthouse. 3 PSI test on nitrogen piping and industrial waste piping order floor PASS
|
||||
| Mechanical Rough-in Inspection | Passed | 9/30/2025 (10:00 - 12:00) | 9/30/2025 (AM) | 09/30/2025 |
|
Corrections:
Miscellaneous/Other
Resolved
09/30/2025
5/12- P-1. 100 PSI air test pass on VAV’s and one AHU. P-3. All fusion welded pipe/AHU tested 100 PSI Hydrostatic test. Passed
|
||||
|
Miscellaneous/Other
Resolved
09/30/2025
5/22- 100 PSI hydrostatic test on chilled water piping in P-3 building. Upper floor mechanical room. Pass
|
||||
|
Miscellaneous/Other
Resolved
09/30/2025
6/4- P-3 100 PSI Hydrostatic test on MUA heating piping in penthouse. 3 PSI test on nitrogen piping and industrial waste piping order floor PASS
|
||||
|
Miscellaneous/Other
Comment Only
09/30/2025
2nd floor P-1 zone 2, ducting installed at this time approved. Went over the scope of what will be happening and what the timelines for cover certain areas will be. Contractor will provide photos as necessary or when needed since areas cannot be shut down for any time period. What is ready to be insulated can be wrapped at this time.
Electrical room addition... ductwork is in and properly supported, more will be installed as progress continues.
|
||||
| Mechanical Rough-in Inspection | Passed | 10/14/2025 (10:00 - 12:00) | 10/14/2025 (AM) | 10/14/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/14/2025
Duct work and supports at building exterior... approved
|
||||
| Mechanical Rough-in Inspection | Passed | 10/30/2025 (10:00 - 12:00) | 10/30/2025 (AM) | 10/30/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/30/2025
Hydro test holding at 100 psi on the chilled/ hot water piping of addition.
|
||||
| Mechanical Rough-in Inspection | Passed | 5/13/2026 (10:00 - 12:00) | 5/13/2026 (AM) | 05/13/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/13/2026
Clean room ducting and install... approved
Pressurization system to the new elevator.. approved pending, the main contractor address the access issue to service the fan and the clearance issue required at the disconnect box... this needs to be addressed by Mortenson const.
|
||||
| Mechanical Final Inspection | Partial Pass | 5/21/2026 (8:00 - 10:00) | 5/21/2026 (AM) | 05/21/2026 |
|
Corrections:
Miscellaneous/Other
Resolved
05/21/2026
5/7- P-1 Pass, waiting for balance reports, P-3 not ready.
|
||||
|
Miscellaneous/Other
Comment Only
05/21/2026
Viewed installed equipment for buildings 1,2,&3... all work is almost complete and operable.
Send balance report to: jaaron@bloomingtonmn.gov
Balance report is neded to final out this permit.
|
||||